11616 W MORRISON ST 91601
Certificate Information: 11616 W MORRISON ST 91601
- Application / Permit
- 21010-20000-02268
- Plan Check / Job No.
- B21VN05578
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 13' X 19'-6" IRREGULAR SHAPED DETACHED REC ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/13/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 7/16/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Applicant returned to address corrections | 8/2/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 8/29/2022 | RAPHAEL ROSAS |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 11/21/2023 | JOHN COLEMAN |
| Permit Finaled | 1/5/2024 | RUBEN SALAS |
| CofO Issued | 1/5/2024 | RUBEN SALAS |
| Permit Finaled | 1/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/3/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 12/7/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/7/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 12/20/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 2/1/2022 | GREGORY HOERNER |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 7/6/2022 | CORREY KITCHENS |
| ZI | Cleared | 7/6/2022 | CORREY KITCHENS |
| ZI | Cleared | 7/6/2022 | CORREY KITCHENS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/19/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/9/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/5/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/3/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 1/20/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 1/20/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 1/24/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 2/6/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 2/22/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/22/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/6/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 10/6/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 10/6/2023 | Approved | THOMAS FINNILA |
| Final | 11/14/2023 | OK to Issue CofO | JOHN COLEMAN |
| Green Building Final | 11/14/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 11/14/2023 | Approved | JOHN COLEMAN |
| Smoke Detectors | 11/14/2023 | Approved | JOHN COLEMAN |