11616 W MORRISON ST 91601

Certificate Information: 11616 W MORRISON ST 91601

Application / Permit
21010-20000-02267
Plan Check / Job No.
B21VN05578
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 48' X 49'-9" IRERGULAR SHAPED 2-STORY SFD WITH ATTACHED TWO-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 RAPHAEL ROSAS
Corrections Issued 7/13/2021 RAPHAEL ROSAS
Quality Review Completed 7/16/2021 STEVEN KIM
Building Plans Picked Up 9/21/2021 APPLICANT
Applicant returned to address corrections 8/2/2022 RAPHAEL ROSAS
Plan Check Approved 8/29/2022 RAPHAEL ROSAS
Issued 9/27/2022 APPLICANT
CofO in Progress 11/21/2023 JOHN COLEMAN
CofO in Progress 11/21/2023 JOHN COLEMAN
Permit Finaled 1/5/2024 RUBEN SALAS
CofO Issued 1/5/2024 RUBEN SALAS
Permit Finaled 1/5/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/3/2021 CARLOS AGUILERA
Permit Cleared 11/3/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/8/2021 CARLOS AGUILERA
Sewer availability Cleared 11/8/2021 CARLOS AGUILERA
Trees in Parkway Cleared 11/30/2021 ADALBERTO VERA
Low Impact Development Cleared 12/7/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/7/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/1/2022 GREGORY HOERNER
Specific Plan Cleared 7/6/2022 CORREY KITCHENS
ZI Cleared 7/6/2022 CORREY KITCHENS
ZI Cleared 7/6/2022 CORREY KITCHENS

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/19/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 11/9/2022 Approved JACK KARGODORIAN
Deputy Wood Construction 11/17/2022 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 12/5/2022 Approved JACK KARGODORIAN
ELECTRICAL-Rough 1/3/2023 Approved JACK KARGODORIAN
HVAC-Rough 1/17/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/20/2023 Approved JACK KARGODORIAN
Green Building Rough 1/20/2023 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 1/20/2023 Approved JACK KARGODORIAN
Shower Pan 1/24/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/1/2023 Partial Approval JACK KARGODORIAN
Insulation 2/6/2023 Approved JACK KARGODORIAN
Drywall Nailing 2/22/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/22/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 7/26/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 10/6/2023 Approved THOMAS FINNILA
HVAC-Final 10/6/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Final 10/6/2023 Approved THOMAS FINNILA
Final 11/14/2023 OK to Issue CofO JOHN COLEMAN
Green Building Final 11/14/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 11/14/2023 SGSOV Approved JOHN COLEMAN
Service/Power Release 11/14/2023 Approved JOHN COLEMAN
Smoke Detectors 11/14/2023 Approved JOHN COLEMAN