8127 N LAUREL CANYON BLVD 91605
Certificate Information: 8127 N LAUREL CANYON BLVD 91605
- Application / Permit
- 21010-20000-02262
- Plan Check / Job No.
- B21VN05563
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'x30' TWO-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | SEAN SHAHMIRI |
| Corrections Issued | 6/22/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 6/29/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/2/2021 | APPLICANT |
| Plan Check Approved | 9/17/2021 | SEAN SHAHMIRI |
| Issued | 9/17/2021 | APPLICANT |
| CofO in Progress | 1/24/2024 | MATTHEW NELSON |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/6/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 8/5/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/5/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 9/8/2021 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/8/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/8/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Reinf. Concrete | 11/15/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 11/19/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 11/30/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Approved | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 1/27/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 1/27/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/2/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/2/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 2/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 2/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 2/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 2/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/31/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 8/31/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 8/31/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 8/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 8/31/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 8/31/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 8/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 8/31/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Final | 1/17/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/17/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 1/17/2024 | Approved | MATTHEW NELSON |
| Final | 1/23/2024 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Approved | MATTHEW NELSON |