13100 W PAXTON ST 91331

Certificate Information: 13100 W PAXTON ST 91331

Application / Permit
21010-20000-02258
Plan Check / Job No.
B21VN05538
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(17) Coffee Shop
Work Description
(N) 1-STORY SHELL BLDG WITH DRIVE-THRU FOR (N) COFFEE SHOP
Permit Issued
Issued on 6/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 NILOOFAR MEHRAIN
Green Plans Picked Up 6/21/2021 APPLICANT
Corrections Issued 6/24/2021 NILOOFAR MEHRAIN
Quality Review Completed 6/24/2021 CHON CHIO KUO
Building Plans Picked Up 6/25/2021 APPLICANT
Applicant returned to address corrections 8/31/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/22/2022 NILOOFAR MEHRAIN
Plan Check Approved 4/6/2023 NILOOFAR MEHRAIN
Issued 6/27/2023 APPLICANT
TCO Issued (Expire Date: 10-08-2025) 4/11/2025 JEFFREY DURAN
CofO in Progress 9/9/2025 JEFFREY DURAN
Permit Finaled 9/9/2025 JEFFREY DURAN
CofO Issued 9/9/2025 JEFFREY DURAN
Permit Finaled 9/9/2025 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 8/12/2021 GABRIEL ROBLES
Green Code Cleared 8/25/2021 MICHAEL AYERS
DAS Clearance Cleared 8/26/2021 NORLITO MEDRANO
Hydrant and Access approval Cleared 10/10/2021 JOHN CONNEALLY
Sewer availability Cleared 6/14/2022 DAGOVERTO GUERRERO
Food Service Establishment Cleared 8/12/2022 RAMESHBHAIR PATEL
Low Impact Development Cleared 8/12/2022 ORVAL HERNANDEZ-MARCI
Permit Cleared 12/13/2022 DAGOVERTO GUERRERO
Highway dedication Cleared 12/23/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/20/2023 CARLOS AGUILERA
Clean Up Green Up Cleared 2/9/2023 MAXFIELD VERMY
Comm Cor/Mini-Mall Cleared 2/9/2023 MAXFIELD VERMY
Comm Cor/Mini-Mall Cleared 2/9/2023 MAXFIELD VERMY
Comm Cor/Mini-Mall Cleared 2/9/2023 MAXFIELD VERMY
Drive-through fast food Cleared 2/9/2023 MAXFIELD VERMY
ZA Case Cleared 2/10/2023 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 4/6/2023 DAGOVERTO GUERRERO
Food establishment approval Cleared 4/6/2023 LACDHS APPROVED

Contact Information

Contractor Americo Builders Llc; Lic. No.: 1060873-B 1040 E HOWELL AVENUE      ANAHEIM, CA 92805

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 8/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/11/2023 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 9/11/2023 Not Ready for Inspection RAFAEL CORTES
Masonry Wall/Backfill 9/13/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/14/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 9/26/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 9/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 9/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/5/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/17/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 10/17/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/18/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 10/27/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 10/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 No Access for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/21/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 11/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 11/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 11/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 12/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/1/2023 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 1/4/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 2/15/2024 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 2/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/12/2024 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 4/17/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/19/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/19/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/19/2024 Partial Inspection DANNY RODRIGUEZ
Insulation 4/23/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/25/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/25/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/25/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/25/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/29/2024 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 7/11/2024 No Access for Inspection DANNY RODRIGUEZ
Special/Order Compliance 9/25/2024 No Access for Inspection DANNY RODRIGUEZ
Final 11/1/2024 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/1/2024 No Access for Inspection DANNY RODRIGUEZ
Green Building Final 11/1/2024 No Access for Inspection DANNY RODRIGUEZ
Green Building Rough 11/1/2024 No Access for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 11/1/2024 No Access for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/1/2024 No Access for Inspection DANNY RODRIGUEZ
Wood Frame 11/1/2024 No Access for Inspection DANNY RODRIGUEZ
Final 2/18/2025 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 2/18/2025 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 2/18/2025 Approved DANNY RODRIGUEZ
Green Building Rough 2/18/2025 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 2/18/2025 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/18/2025 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/18/2025 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 2/24/2025 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 2/24/2025 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/11/2025 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 3/12/2025 No Access for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 3/13/2025 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/14/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 3/19/2025 Conditional Approval DANNY RODRIGUEZ
Final 8/26/2025 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 8/26/2025 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved GREGORY POMISH
Verify Sprinkler Sign Off 8/26/2025 Approved GREGORY POMISH
Wood Frame 8/26/2025 Approved GREGORY POMISH
Final 9/9/2025 OK to Issue CofO JEFFREY DURAN