1126 E VICTORIA AVE 90291

Certificate Information: 1126 E VICTORIA AVE 90291

Application / Permit
21010-20000-02241
Plan Check / Job No.
B21VN05474
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 51'-2" x 73'-7.5" IRR. SHAPED TWO-STORY SINGLE FAMILY DWELLING; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 12/22/2021
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 SEAN SHAHMIRI
Corrections Issued 6/12/2021 SEAN SHAHMIRI
Quality Review Completed 6/22/2021 OMID HEDAYAT
Applicant returned to address corrections 10/29/2021 SEAN SHAHMIRI
Applicant returned to address corrections 11/16/2021 SEAN SHAHMIRI
Applicant returned to address corrections 11/17/2021 SEAN SHAHMIRI
Plan Check Approved 12/3/2021 SEAN SHAHMIRI
Issued 12/22/2021 APPLICANT
Building Plans Picked Up 12/27/2021 APPLICANT
CofO in Progress 4/10/2024 HERBERT GIRON
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

"Q" conditions Cleared 7/9/2021 MIGUEL GAMBOA
Address approval Cleared 7/13/2021 DINAH GARIN
Sewer availability Cleared 7/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/14/2021 DINAH GARIN
Specific Plan Cleared 7/22/2021 PETE EYRE
Hydrant and Access approval Cleared 9/6/2021 JOHN CONNEALLY
Low Impact Development Cleared 11/3/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/5/2021 DINAH GARIN

Contact Information

Architect Hamilton,, Peter W; Lic. No.: C37714 1444 COLBY AVENUE #1      LOS ANGELES, CA 90025
Contractor Owner-Builder       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/31/2022 Partial Approval DAVID FEILER
Footing/Foundation/Slab 2/22/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 3/11/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 7/29/2022 No Access for Inspection DAVID FEILER
HVAC-Rough 8/23/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 10/4/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 10/19/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 10/19/2022 Approved DAVID FEILER
ELECTRICAL-Rough 11/1/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 11/2/2022 Corrections Issued DAVID FEILER
Green Building Rough 11/2/2022 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 11/2/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Conditional Approval DAVID FEILER
Green Building Rough 11/14/2022 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 11/14/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 11/22/2022 Partial Approval DAVID FEILER
Interior/Exterior Lathing 1/5/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 1/9/2023 Corrections Issued EVAN COOPER
Green Building Rough 1/9/2023 Approved EVAN COOPER
Verify Sprinkler Sign Off 1/9/2023 Not Ready for Inspection EVAN COOPER
Insulation 1/18/2023 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 1/26/2023 Not Ready for Inspection EVAN COOPER
Shower Pan 1/26/2023 Approved EVAN COOPER
Interior/Exterior Lathing 2/2/2023 Approved HERBERT GIRON
Drywall Nailing 2/8/2023 Approved EVAN COOPER
Sewer 2/8/2023 Approved EVAN COOPER
Sewer 2/9/2023 Approved EVAN COOPER
Gas Test 10/25/2023 Approved HERBERT GIRON
Gas Test 11/28/2023 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Final 12/12/2023 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 12/12/2023 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 12/22/2023 Approved TEMISTOCLES CAAL
HVAC-Final 12/29/2023 No Access for Inspection TEMISTOCLES CAAL
HVAC-Final 1/4/2024 Approved HERBERT GIRON
Gas Test 1/5/2024 Approved HERBERT GIRON
PLUMBING-Final 1/5/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 2/16/2024 Approved HERBERT GIRON
Special/Order Compliance 2/22/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 3/19/2024 Corrections Issued HERBERT GIRON
Final 3/19/2024 Corrections Issued HERBERT GIRON
Green Building Final 3/19/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Approved HERBERT GIRON
Service/Power Release 3/19/2024 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 3/19/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 4/5/2024 Not Ready for Inspection HERBERT GIRON
Final 4/5/2024 Corrections Issued HERBERT GIRON
Service/Power Release 4/5/2024 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 4/9/2024 Approved HERBERT GIRON
Final 4/9/2024 OK to Issue CofO HERBERT GIRON
Service/Power Release 4/9/2024 Approved HERBERT GIRON