483 3/4 E 49TH ST 90011

Certificate Information: 483 3/4 E 49TH ST 90011

Application / Permit
21010-20000-02224
Plan Check / Job No.
B21VN05443
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27'-7" X 32' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) . ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/11/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2021 APPLICANT
Assigned to Plan Check Engineer 5/24/2021 RAPHAEL ROSAS
Corrections Issued 5/25/2021 RAPHAEL ROSAS
Applicant returned to address corrections 7/6/2021 RAPHAEL ROSAS
Applicant returned to address corrections 7/20/2021 RAPHAEL ROSAS
Plan Check Approved 10/21/2021 RAPHAEL ROSAS
Building Plans Picked Up 10/25/2021 APPLICANT
Issued 11/11/2021 APPLICANT
CofO in Progress 8/3/2022 JOAQUIN GREENOUGH
Permit Finaled 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/17/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/22/2021 STEVE MELGAR
Sewer availability Cleared 6/22/2021 STEVE MELGAR
Hydrant and Access approval Cleared 9/11/2021 RUEL COLE
Low Impact Development Cleared 9/22/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/7/2021 STEVE MELGAR

Contact Information

Contractor Good News Construction Inc; Lic. No.: 967654-B 15130 VENTURA BLVE STE 329      SHERMAN OAKS, CA 91403
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/17/2021 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/23/2021 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 11/30/2021 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/1/2021 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 12/6/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/8/2021 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 12/14/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/8/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Wood Construction 2/8/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 2/8/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 2/8/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 2/8/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 2/11/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 2/11/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 2/11/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/16/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 2/16/2022 Approved JOAQUIN GREENOUGH
Insulation 2/16/2022 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 2/16/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 2/23/2022 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Rough 2/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/23/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 3/10/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Final 3/15/2022 Approved JOAQUIN GREENOUGH
Sewer 3/15/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 3/15/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 4/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Gas Test 4/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/26/2022 Approved HORACE FULTZ
Drywall Nailing 5/26/2022 Approved HORACE FULTZ
Final 5/26/2022 Partial Approval HORACE FULTZ
Green Building Final 5/26/2022 Approved HORACE FULTZ
Green Building Rough 5/26/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Approved HORACE FULTZ
Service/Power Release 5/26/2022 Approved HORACE FULTZ
Smoke Detectors 5/26/2022 Approved HORACE FULTZ
Final 7/12/2022 Corrections Issued JOAQUIN GREENOUGH
Final 8/1/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 8/1/2022 Conditional Approval JOAQUIN GREENOUGH