20537 W OVERLOOK CT 91326

Certificate Information: 20537 W OVERLOOK CT 91326

Application / Permit
21010-20000-02215
Plan Check / Job No.
B21VN05420
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(TRACK 50505_LOT 48) PROPOSE NEW SFD WITH ATTACHED GARAGE _ PER STANDARD PLAN# 655_5C [BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D].
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 1/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 DAWN MC NULTY
Corrections Issued 6/7/2021 DAWN MC NULTY
Quality Review Completed 6/14/2021 STEVEN KIM
Building Plans Picked Up 8/17/2021 APPLICANT
Plan Check Approved 1/11/2022 DAWN MC NULTY
Issued 1/18/2022 APPLICANT
CofO in Progress 12/20/2022 HENRY KIM
Permit Finaled 1/12/2023 MICHAEL SMITH
CofO Issued 1/12/2023 MICHAEL SMITH
Permit Finaled 1/12/2023 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 9/22/2021 LAUREN PADICK
Address approval Cleared 9/22/2021 LEE GUILBEAUX
CPC Cleared 9/22/2021 LAUREN PADICK
CPC Cleared 9/22/2021 LAUREN PADICK
CPC Cleared 9/22/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 9/22/2021 LEE GUILBEAUX
Permit Cleared 9/22/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/22/2021 LEE GUILBEAUX
Sewer availability Cleared 9/22/2021 LEE GUILBEAUX
Tract Map conditions Cleared 9/22/2021 LAUREN PADICK
ZA Case Cleared 9/22/2021 LAUREN PADICK
ZA Case Cleared 9/22/2021 LAUREN PADICK
ZI Cleared 9/22/2021 LAUREN PADICK
Public Works-Highway Ded. Cleared 9/22/2021 LEE GUILBEAUX
Low Impact Development Cleared 9/28/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 12/7/2021 ROBERT DUFF

Contact Information

Architect Swift,, Daniel R; Lic. No.: C32860 4601 WESTOWN PARKWAY SUITE 208      WEST DES MOINES, IA 50266
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Hattar,, Basil Ibrahim; Lic. No.: GE2734 41837 SONOMA ROAD      PALMDALE, CA 93551
Engineer Wong,, Ramon Roman; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/28/2022 Approved SEAN WIRCH
Footing/Foundation/Slab 3/16/2022 Approved SEAN WIRCH
METHANE-Barrier 3/16/2022 Approved SEAN WIRCH
METHANE-Subgrade 3/16/2022 Approved SEAN WIRCH
Deputy Reinf. Concrete 4/13/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Partial Approval HENRY KIM
Deputy Wood Construction 8/3/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 9/1/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 9/1/2022 Approved JEFFREY PARD
Green Building Rough 9/1/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 9/1/2022 Approved JEFFREY PARD
METHANE-Rough 9/1/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 9/1/2022 Corrections Issued JEFFREY PARD
Verify Sprinkler Sign Off 9/1/2022 Approved JEFFREY PARD
PLUMBING-Rough 9/6/2022 Approved HENRY KIM
Underground Mechanical 9/6/2022 Approved HENRY KIM
BUILDING-Rough-Frame 9/8/2022 Approved HENRY KIM
Green Building Rough 9/8/2022 Approved HENRY KIM
Interior/Exterior Lathing 9/8/2022 Partial Approval HENRY KIM
METHANE-Rough 9/8/2022 Approved HENRY KIM
Drywall Nailing 9/26/2022 Approved JEFFREY PARD
Gas Test 10/26/2022 Approved HENRY KIM
Service/Power Release 11/7/2022 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved HENRY KIM
Service/Power Release 11/9/2022 Partial Inspection HENRY KIM
Service/Power Release 11/14/2022 Corrections Issued HENRY KIM
Service/Power Release 11/16/2022 Not Ready for Inspection JEFFREY PARD
Service/Power Release 11/18/2022 Approved HENRY KIM
ELECTRICAL-Final 12/15/2022 Corrections Issued HENRY KIM
Final 12/15/2022 Corrections Issued HENRY KIM
Green Building Final 12/15/2022 Approved HENRY KIM
HVAC-Final 12/15/2022 Corrections Issued HENRY KIM
PLUMBING-Final 12/15/2022 Corrections Issued HENRY KIM
Smoke Detectors 12/15/2022 Approved HENRY KIM
ELECTRICAL-Final 12/16/2022 Approved HENRY KIM
Final 12/16/2022 Corrections Issued HENRY KIM
HVAC-Final 12/16/2022 Approved HENRY KIM
PLUMBING-Final 12/16/2022 Approved HENRY KIM
Final 12/19/2022 OK to Issue CofO HENRY KIM
Sewer 12/21/2022 Approved HENRY KIM