20549 W OVERLOOK CT 91326
Certificate Information: 20549 W OVERLOOK CT 91326
- Application / Permit
- 21010-20000-02213
- Plan Check / Job No.
- B21VN05420
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (TRACK 50505_LOT 46) PROPOSE NEW SFD WITH ATTACHED GARAGE _ PER STANDARD PLAN# 655_6B [BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D].
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 1/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | DAWN MC NULTY |
| Corrections Issued | 6/7/2021 | DAWN MC NULTY |
| Quality Review Completed | 6/14/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| Plan Check Approved | 1/11/2022 | DAWN MC NULTY |
| Issued | 1/18/2022 | APPLICANT |
| CofO in Progress | 1/21/2023 | HENRY KIM |
| Permit Finaled | 1/23/2023 | MICHAEL SMITH |
| CofO Issued | 1/23/2023 | MICHAEL SMITH |
| Permit Finaled | 1/23/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 9/22/2021 | LAUREN PADICK |
| Address approval | Cleared | 9/22/2021 | LEE GUILBEAUX |
| CPC | Cleared | 9/22/2021 | LAUREN PADICK |
| CPC | Cleared | 9/22/2021 | LAUREN PADICK |
| CPC | Cleared | 9/22/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | LEE GUILBEAUX |
| Permit | Cleared | 9/22/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/22/2021 | LEE GUILBEAUX |
| Tract Map conditions | Cleared | 9/22/2021 | LAUREN PADICK |
| ZA Case | Cleared | 9/22/2021 | LAUREN PADICK |
| ZA Case | Cleared | 9/22/2021 | LAUREN PADICK |
| ZI | Cleared | 9/22/2021 | LAUREN PADICK |
| Public Works-Highway Ded. | Cleared | 9/22/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 9/28/2021 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 12/7/2021 | ROBERT DUFF |
Contact Information
| Architect | Swift,, Daniel R; Lic. No.: C32860 | 4601 WESTOWN PARKWAY SUITE 208 WEST DES MOINES, IA 50266 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Hattar,, Basil Ibrahim; Lic. No.: GE2734 | 41837 SONOMA ROAD PALMDALE, CA 93551 |
| Engineer | Wong,, Ramon Roman; Lic. No.: S2345 | 1800 E. 16TH STREET SANTA ANA, CA 92701 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/23/2022 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 3/17/2022 | Approved | SEAN WIRCH |
| METHANE-Barrier | 3/17/2022 | Approved | SEAN WIRCH |
| METHANE-Subgrade | 3/17/2022 | Approved | SEAN WIRCH |
| Pre-Inspection | 3/17/2022 | Corrections Issued | SEAN WIRCH |
| Deputy Reinf. Concrete | 4/12/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Partial Approval | SEAN WIRCH |
| Deputy Wood Construction | 8/3/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | HENRY KIM |
| Underground Mechanical | 8/30/2022 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 9/6/2022 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 9/9/2022 | Approved | HENRY KIM |
| Green Building Rough | 9/9/2022 | Approved | HENRY KIM |
| HVAC-Rough | 9/9/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/9/2022 | Partial Approval | HENRY KIM |
| METHANE-Rough | 9/9/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 9/9/2022 | Approved | HENRY KIM |
| Special/Order Compliance | 9/9/2022 | Corrections Issued | HENRY KIM |
| Verify Sprinkler Sign Off | 9/9/2022 | Approved | HENRY KIM |
| Drywall Nailing | 10/3/2022 | Approved | JEFFREY PARD |
| Gas Test | 10/26/2022 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Approved | HENRY KIM |
| Service/Power Release | 11/9/2022 | Partial Inspection | HENRY KIM |
| Service/Power Release | 11/14/2022 | Corrections Issued | HENRY KIM |
| Service/Power Release | 11/16/2022 | Not Ready for Inspection | JEFFREY PARD |
| Service/Power Release | 11/28/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 1/5/2023 | Corrections Issued | HENRY KIM |
| HVAC-Final | 1/5/2023 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 1/5/2023 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 1/13/2023 | Approved | HENRY KIM |
| Final | 1/13/2023 | Corrections Issued | HENRY KIM |
| Green Building Final | 1/13/2023 | Approved | HENRY KIM |
| HVAC-Final | 1/13/2023 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Final | 1/13/2023 | Approved | HENRY KIM |
| Smoke Detectors | 1/13/2023 | Approved | HENRY KIM |
| ELECTRICAL-Final | 1/20/2023 | Approved | HENRY KIM |
| Final | 1/20/2023 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 1/20/2023 | Approved | HENRY KIM |
| PLUMBING-Final | 1/20/2023 | Approved | HENRY KIM |
| Sewer | 1/23/2023 | Approved | HENRY KIM |