15129 W LEADWELL ST 91405
Certificate Information: 15129 W LEADWELL ST 91405
- Application / Permit
- 21010-20000-02203
- Plan Check / Job No.
- B21VN05375
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28' X 24' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/10/2021 | SELLA BENYAMIN |
| Quality Review Completed | 6/14/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/15/2021 | APPLICANT |
| Plan Check Approved | 9/2/2022 | SELLA BENYAMIN |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 6/29/2023 | GREGG CUMMINGS |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/5/2022 | DWIGHT SANKEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/1/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/2/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 9/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 9/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 9/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 9/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Approved | WILLIAM WREN |
| Deputy Wood Construction | 9/27/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/30/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/30/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 9/30/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 9/30/2022 | Approved | GREGG CUMMINGS |
| Sewer | 9/30/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/7/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/7/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/7/2022 | Approved | GREGG CUMMINGS |
| Insulation | 10/7/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 10/7/2022 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 10/14/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/21/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/1/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 2/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/17/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/17/2023 | Approved | GREGG CUMMINGS |
| HVAC-Final | 2/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 2/17/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/17/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/28/2023 | Approved | GREGG CUMMINGS |
| Final | 6/28/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 6/28/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 6/28/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 6/28/2023 | Approved | GREGG CUMMINGS |