3213-3213 1/2 N DREW ST 90065
Certificate Information: 3213-3213 1/2 N DREW ST 90065
- Application / Permit
- 21010-20000-02201
- Plan Check / Job No.
- B21VN05372
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (40'-0"x 25'-0") ONE- STORY DETACHED TWO ACCESSORY DWELLING UNITS PER GCS 56852.2 (e) (1) (D) and LAMC 12.22 A.33 (c), (d) and (g). WORK PER ENGINEER. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
- Permit Issued
- Issued on 1/25/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | TROY DEGUZMAN |
| Corrections Issued | 6/23/2021 | TROY DEGUZMAN |
| Quality Review Completed | 6/24/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/2/2021 | APPLICANT |
| Applicant returned to address corrections | 9/29/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 10/28/2022 | MADISON ODELL |
| Applicant returned to address corrections | 12/2/2022 | SELLA BENYAMIN |
| Plan Check Approved | 1/24/2023 | SELLA BENYAMIN |
| Issued | 1/25/2023 | APPLICANT |
| CofO in Progress | 4/18/2025 | ALIZAH MAYAGOITIA |
| CofO Issued | 4/23/2025 | DEROLD HAUFF |
| Permit Finaled | 4/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 11/23/2021 | PAMELA TENEZA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2021 | THAN WIN |
| Supp. Use District POD/CDO/TDO | Cleared | 10/17/2022 | NASHYA JENSEN |
| ZI | Cleared | 10/17/2022 | NASHYA JENSEN |
| ZI | Cleared | 10/17/2022 | NASHYA JENSEN |
| Grading Pre-Inspection | Cleared | 11/2/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 12/2/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Bartelle,, Kristofer Grimm; Lic. No.: C84617 | 19900 ACRE ST LOS ANGELES, CA 91324 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 3/23/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/17/2023 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/15/2023 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/31/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/12/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/5/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/5/2024 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/5/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/19/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/19/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 3/19/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 3/19/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 4/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 4/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 4/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 4/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/18/2024 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/18/2024 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/25/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 5/6/2024 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 5/9/2024 | Approved | JOSH MEISTER |
| Shower Pan | 5/28/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/30/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 3/6/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 3/6/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/6/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 3/6/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/6/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 3/6/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Smoke Detectors | 3/6/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/12/2025 | Approved | NICHOLAS LOPEZ |
| Final | 4/16/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Final | 4/16/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Service/Power Release | 4/16/2025 | Approved | NICHOLAS LOPEZ |
| Final | 4/18/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 4/18/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/18/2025 | Approved | ALIZAH MAYAGOITIA |