6747 N ATOLL AVE 91606

Certificate Information: 6747 N ATOLL AVE 91606

Application / Permit
21010-20000-02194
Plan Check / Job No.
B21VN05337
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-4" x 33' TWO-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 9/15/2022
Issuing Office
Current Status
CofO Issued on 2/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 SEAN SHAHMIRI
Corrections Issued 6/6/2021 SEAN SHAHMIRI
Quality Review Completed 6/21/2021 OMID HEDAYAT
Applicant returned to address corrections 8/30/2022 SEAN SHAHMIRI
Plan Check Approved 9/15/2022 SEAN SHAHMIRI
Issued 9/15/2022 APPLICANT
CofO in Progress 12/15/2023 JOSE AVILA
Permit Finaled 2/5/2024 RUBEN SALAS
Permit Finaled 2/5/2024 RUBEN SALAS
CofO Issued 2/5/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 8/20/2021 WALTER RAMIREZ
Address approval Cleared 10/1/2021 CARLOS AGUILERA
Sewer availability Cleared 10/5/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/12/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/1/2022 GREGORY HOERNER
Low Impact Development Cleared 8/17/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/29/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/1/2023 Partial Approval KIRK SANDERS
Underground Mechanical 5/1/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 5/4/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Corrections Issued KIRK SANDERS
Deputy Wood Construction 5/16/2023 Conditional Approval MICHAEL SMITH
ELECTRICAL-Rough 6/26/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Corrections Issued KIRK SANDERS
Gas Test 6/26/2023 Partial Approval KIRK SANDERS
HVAC-Rough 6/26/2023 Approved KIRK SANDERS
PLUMBING-Rough 6/26/2023 Corrections Issued KIRK SANDERS
Rough-Elec/Plmb/HVAC 6/26/2023 Partial Approval KIRK SANDERS
Deputy Wood Construction 6/27/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 7/6/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 7/6/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved KIRK SANDERS
Green Building Rough 7/6/2023 Approved KIRK SANDERS
HVAC-Rough 7/6/2023 Approved KIRK SANDERS
PLUMBING-Rough 7/6/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 7/6/2023 Approved KIRK SANDERS
Insulation 7/10/2023 Corrections Issued KIRK SANDERS
Insulation 7/17/2023 Approved JUAN VALENZUELA
Shower Pan 7/17/2023 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 7/18/2023 Approved KIRK SANDERS
Shower Pan 7/18/2023 Approved KIRK SANDERS
Drywall Nailing 7/24/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 7/24/2023 Approved KIRK SANDERS
Sewer 9/13/2023 Not Ready for Inspection KIRK SANDERS
Gas Test 9/19/2023 Approved CHRISTOPHER ROJAS
Gas Test 9/22/2023 Approved CHRISTOPHER ROJAS
Sewer 9/22/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 11/14/2023 Corrections Issued KIRK SANDERS
Final 11/14/2023 Corrections Issued KIRK SANDERS
Green Building Final 11/14/2023 Approved KIRK SANDERS
HVAC-Final 11/14/2023 Approved KIRK SANDERS
PLUMBING-Final 11/14/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/14/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 11/14/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 11/14/2023 Approved KIRK SANDERS
ELECTRICAL-Final 12/1/2023 Approved MEL KHACHATOURIAN
Final 12/1/2023 Partial Approval MEL KHACHATOURIAN
HVAC-Final 12/1/2023 Approved MEL KHACHATOURIAN
PLUMBING-Final 12/1/2023 Approved MEL KHACHATOURIAN
Service/Power Release 12/1/2023 Approved MEL KHACHATOURIAN
Final 12/14/2023 OK to Issue CofO JOSE AVILA