12531 N SADDLE CT 91326

Certificate Information: 12531 N SADDLE CT 91326

Application / Permit
21010-20000-02166
Plan Check / Job No.
B21VN05253
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE SFD W/ ATTACHED GARAGE_STANDARD PLAN #654, PLAN 5BR [BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D].
Permit Issued
Issued on 12/15/2021
Issuing Office
Current Status
CofO Issued on 10/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 DAWN MC NULTY
Corrections Issued 6/7/2021 DAWN MC NULTY
Quality Review Completed 6/14/2021 STEVEN KIM
Building Plans Picked Up 8/12/2021 APPLICANT
Applicant returned to address corrections 12/7/2021 DAWN MC NULTY
Plan Check Approved 12/12/2021 DAWN MC NULTY
Issued 12/15/2021 APPLICANT
CofO in Progress 10/18/2022 JEFFREY PARD
CofO Issued 10/19/2022 MICHAEL SMITH
Permit Finaled 10/19/2022 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 10/14/2021 DANG NGUYEN
Address approval Cleared 10/14/2021 LEE GUILBEAUX
CPC Cleared 10/14/2021 DANG NGUYEN
CPC Cleared 10/14/2021 DANG NGUYEN
CPC Cleared 10/14/2021 DANG NGUYEN
Permit Cleared 10/14/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/14/2021 LEE GUILBEAUX
Specific Plan Cleared 10/14/2021 DANG NGUYEN
Tract Map conditions Cleared 10/14/2021 DANG NGUYEN
Tract Map conditions Cleared 10/14/2021 DANG NGUYEN
ZA Case Cleared 10/14/2021 DANG NGUYEN
ZA Case Cleared 10/14/2021 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 10/18/2021 LEE GUILBEAUX
Sewer availability Cleared 10/18/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/18/2021 LEE GUILBEAUX
Low Impact Development Cleared 10/21/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 12/2/2021 ROBERT DUFF

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/3/2022 Partial Approval HENRY KIM
Footing/Foundation/Slab 2/18/2022 Approved HENRY KIM
Deputy Reinf. Concrete 2/22/2022 Conditional Approval HENRY KIM
Sewer 3/8/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Not Ready for Inspection HENRY KIM
Deputy Drilled-In Anchors 4/19/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Conditional Approval HENRY KIM
Deputy Wood Construction 4/28/2022 Approved SEAN WIRCH
Underground Mechanical 5/2/2022 Partial Approval HENRY KIM
Deputy Drilled-In Anchors 5/31/2022 Conditional Approval SEAN WIRCH
Deputy Wood Construction 5/31/2022 Conditional Approval SEAN WIRCH
ELECTRICAL-Rough 6/1/2022 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Not Ready for Inspection HENRY KIM
HVAC-Rough 6/1/2022 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 6/17/2022 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Approval HENRY KIM
HVAC-Rough 6/17/2022 Approved HENRY KIM
PLUMBING-Rough 6/17/2022 Approved HENRY KIM
BUILDING-Rough-Frame 6/23/2022 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 6/23/2022 Approved HENRY KIM
Green Building Rough 6/23/2022 Corrections Issued HENRY KIM
Interior/Exterior Lathing 6/23/2022 Not Ready for Inspection HENRY KIM
Verify Sprinkler Sign Off 6/23/2022 Approved HENRY KIM
Interior/Exterior Lathing 6/27/2022 Partial Approval HENRY KIM
BUILDING-Rough-Frame 6/29/2022 Approved HENRY KIM
Green Building Rough 6/29/2022 Approved HENRY KIM
Insulation 6/29/2022 Corrections Issued HENRY KIM
Special/Order Compliance 7/5/2022 Approved HENRY KIM
Drywall Nailing 7/14/2022 Approved HENRY KIM
Interior/Exterior Lathing 7/18/2022 Approved HENRY KIM
Gas Test 8/17/2022 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved HENRY KIM
Service/Power Release 9/16/2022 Approved JEFFREY PARD
ELECTRICAL-Final 10/11/2022 Corrections Issued HENRY KIM
Green Building Final 10/11/2022 Corrections Issued HENRY KIM
HVAC-Final 10/11/2022 Corrections Issued HENRY KIM
PLUMBING-Final 10/11/2022 Approved HENRY KIM
Verify Rec and Parks Fee Memo 10/11/2022 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 10/13/2022 Approved JEFFREY PARD
HVAC-Final 10/13/2022 Approved JEFFREY PARD
Final 10/17/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 10/17/2022 Approved JEFFREY PARD
Smoke Detectors 10/17/2022 Approved JEFFREY PARD