14552 W ORO GRANDE ST 91342
Certificate Information: 14552 W ORO GRANDE ST 91342
- Application / Permit
- 21010-20000-02160
- Plan Check / Job No.
- B21VN05231
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23' x 38' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/30/2022
- Issuing Office
- Current Status
- CofO in Progress on 9/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/1/2021 | SELLA BENYAMIN |
| Quality Review Completed | 6/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Plan Check Approved | 6/29/2022 | SELLA BENYAMIN |
| Issued | 6/30/2022 | APPLICANT |
| CofO in Progress | 9/12/2025 | KEVIN BERBERYAN |
| CofO in Progress | 9/25/2025 | KEVIN BERBERYAN |
| CofO in Progress | 4/24/2026 | KEVIN BERBERYAN |
| CofO in Progress | 5/13/2026 | JOSE AVILA |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/4/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 11/19/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/24/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 4/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mena,, Rolando A; Lic. No.: C50331 | 544 1/2 BRITTANIA ST #A LOS ANGELES, CA 90033 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/19/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/19/2022 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 7/25/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 7/25/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/26/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 7/26/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 7/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/3/2022 | Partial Approval | DEANDRE HOFFMAN |
| Underground Mechanical | 8/3/2022 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 8/10/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/13/2023 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/13/2023 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 11/13/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 11/13/2023 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/13/2023 | Corrections Issued | KEVIN BERBERYAN |
| Shower Pan | 11/13/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 11/13/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 12/6/2023 | Conditional Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/6/2023 | Approved | KEVIN BERBERYAN |
| Sewer | 12/6/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Drywall Nailing | 1/16/2024 | Approved | MICHEL ABAJAN |
| Sewer | 1/16/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/23/2025 | Approved | KEVIN BERBERYAN |
| Final | 6/23/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 6/23/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 6/23/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 6/23/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 6/23/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/10/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/10/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 9/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 9/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| Service/Power Release | 9/12/2025 | Approved | KEVIN BERBERYAN |
| Final | 4/24/2026 | OK to Issue CofO | KEVIN BERBERYAN |