11201 W VALLEY SPRING LANE 91602

Certificate Information: 11201 W VALLEY SPRING LANE 91602

Application / Permit
21010-20000-02118
Plan Check / Job No.
B21VN05073
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 13' X 18' DETACHED REC ROOM WITH ATTACHED 10' X 18' TRELLIS
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 SELLA BENYAMIN
Corrections Issued 5/25/2021 SELLA BENYAMIN
Quality Review Completed 5/27/2021 STEVEN KIM
Building Plans Picked Up 6/1/2021 APPLICANT
Applicant returned to address corrections 11/23/2021 SELLA BENYAMIN
Plan Check Approved 12/9/2021 SELLA BENYAMIN
Issued 12/9/2021 APPLICANT
CofO in Progress 8/12/2022 THOMAS FINNILA
CofO in Progress 8/12/2022 THOMAS FINNILA
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/1/2021 CARLOS AGUILERA
ZI Cleared 7/1/2021 LAUREN PADICK
Low Impact Development Cleared 9/17/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 9/20/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/5/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 1/13/2022 Approved MATT KELLERMAN
Deputy Reinf. Concrete 1/14/2022 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 3/9/2022 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 3/9/2022 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 3/9/2022 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 3/9/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 3/17/2022 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 3/17/2022 Not Ready for Inspection DAVID MATSON
Verify Sprinkler Sign Off 3/17/2022 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 3/21/2022 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 3/25/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 8/10/2022 Approved THOMAS FINNILA
Final 8/10/2022 OK to Issue CofO THOMAS FINNILA
MERV13>=Final 8/10/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Approved THOMAS FINNILA
Service/Power Release 8/10/2022 Approved THOMAS FINNILA
Smoke Detectors 8/10/2022 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 8/10/2022 Approved THOMAS FINNILA