11201 W VALLEY SPRING LANE 91602
Certificate Information: 11201 W VALLEY SPRING LANE 91602
- Application / Permit
- 21010-20000-02117
- Plan Check / Job No.
- B21VN05073
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 59'-9" X 48'-5" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | SELLA BENYAMIN |
| Corrections Issued | 5/25/2021 | SELLA BENYAMIN |
| Quality Review Completed | 5/27/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| Applicant returned to address corrections | 11/23/2021 | SELLA BENYAMIN |
| Plan Check Approved | 12/9/2021 | SELLA BENYAMIN |
| Issued | 12/9/2021 | APPLICANT |
| CofO in Progress | 8/9/2022 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | CARLOS AGUILERA |
| Permit | Cleared | 7/1/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/1/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/6/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 9/17/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 9/20/2021 | CARLOS AGUILERA |
| ZI | Cleared | 10/6/2021 | LAUREN PADICK |
| Trees in Parkway | Cleared | 11/10/2021 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 12/17/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 12/21/2021 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 12/21/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/5/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 1/6/2022 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/13/2022 | Approved | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/24/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 2/24/2022 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 2/24/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 2/24/2022 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 2/24/2022 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 3/4/2022 | Corrections Issued | THOMAS FINNILA |
| Deputy Wood Construction | 3/7/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/9/2022 | Order to Comply Issued | THOMAS FINNILA |
| Green Building Rough | 3/9/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/9/2022 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 3/9/2022 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 3/9/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/17/2022 | Not Ready for Inspection | DAVID MATSON |
| Verify Sprinkler Sign Off | 3/17/2022 | Not Ready for Inspection | DAVID MATSON |
| Wood Frame | 3/17/2022 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 3/21/2022 | Conditional Approval | THOMAS FINNILA |
| Insulation | 3/25/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/25/2022 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 3/25/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/4/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 4/4/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/7/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 4/7/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/15/2022 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 7/15/2022 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/29/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 7/29/2022 | Corrections Issued | THOMAS FINNILA |
| Gas Test | 7/29/2022 | Approved | THOMAS FINNILA |
| Green Building Final | 7/29/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/29/2022 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Final | 7/29/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 7/29/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 7/29/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 7/29/2022 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/29/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 8/8/2022 | Approved | THOMAS FINNILA |
| Final | 8/8/2022 | OK to Issue CofO | THOMAS FINNILA |
| HVAC-Final | 8/8/2022 | Approved | THOMAS FINNILA |
| Service/Power Release | 8/8/2022 | Approved | THOMAS FINNILA |