9422 N URBANA AVE 91331

Certificate Information: 9422 N URBANA AVE 91331

Application / Permit
21010-20000-02110
Plan Check / Job No.
B21VN05035
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 28'-0" X 21'-9", 1,034 SQ. FT. 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A33 (c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/19/2021
Issuing Office
Current Status
CofO Issued on 11/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 COLIN LOREDO
Corrections Issued 6/4/2021 COLIN LOREDO
Quality Review Completed 6/8/2021 OMID HEDAYAT
Building Plans Picked Up 6/11/2021 APPLICANT
Applicant returned to address corrections 8/19/2021 COLIN LOREDO
Plan Check Approved 8/19/2021 COLIN LOREDO
Issued 8/19/2021 APPLICANT
CofO in Progress 10/23/2023 GREGG CUMMINGS
Permit Finaled 11/24/2023 RUBEN SALAS
CofO Issued 11/24/2023 RUBEN SALAS
Permit Finaled 11/24/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/8/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/15/2021 CARLOS AGUILERA
Sewer availability Cleared 6/15/2021 CARLOS AGUILERA
Construction near power lines Cleared 7/8/2021 RIDWAN HARDY
Low Impact Development Cleared 8/13/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/14/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/7/2021 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/15/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 10/15/2021 Approved GREGG CUMMINGS
Wood Frame 10/27/2021 Partial Approval GREGG CUMMINGS
Deputy Wood Construction 11/4/2021 Conditional Approval WILLIAM WREN
BUILDING-Rough-Frame 11/12/2021 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 11/12/2021 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Partial Approval GREGG CUMMINGS
HVAC-Rough 11/12/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 11/12/2021 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 11/22/2021 Approved MATTHEW NELSON
Green Building Rough 11/22/2021 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 11/22/2021 Approved MATTHEW NELSON
Sewer 11/29/2021 Approved WILLIAM WREN
Underground Mechanical 11/29/2021 Approved WILLIAM WREN
ELECTRICAL-Rough 12/6/2021 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/6/2021 Partial Approval JENNIFER RABUCHIN
Insulation 12/14/2021 Corrections Issued WILLIAM WREN
Insulation 12/17/2021 Approved WILLIAM WREN
Shower Pan 12/17/2021 Approved WILLIAM WREN
Drywall Nailing 12/21/2021 Approved CLAYTON GRAHAM
ELECTRICAL-Rough 1/6/2022 Corrections Issued GREGG CUMMINGS
Underground Mechanical 1/6/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 2/24/2022 Approved WILLIAM WREN
Final 6/6/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 6/6/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Approved GREGG CUMMINGS
Service/Power Release 6/6/2022 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 6/6/2022 Approved GREGG CUMMINGS
Final 6/24/2022 Corrections Issued GREGG CUMMINGS
Final 9/6/2022 Not Ready for Inspection DEANDRE HOFFMAN
Service/Power Release 9/6/2022 Not Ready for Inspection DEANDRE HOFFMAN
Final 10/16/2023 Corrections Issued GREGG CUMMINGS
Service/Power Release 10/16/2023 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 10/20/2023 Approved GREGG CUMMINGS
Final 10/20/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 10/20/2023 Approved GREGG CUMMINGS
PLUMBING-Final 10/20/2023 Approved GREGG CUMMINGS
Service/Power Release 10/20/2023 Approved GREGG CUMMINGS