4740 N SUNNYSLOPE AVE 91423
Certificate Information: 4740 N SUNNYSLOPE AVE 91423
- Application / Permit
- 21010-20000-02109
- Plan Check / Job No.
- B21VN05033
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 43' X 54'-7" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | SELLA BENYAMIN |
| Corrections Issued | 5/20/2021 | SELLA BENYAMIN |
| Quality Review Completed | 5/20/2021 | STEVEN KIM |
| Building Plans Picked Up | 5/21/2021 | APPLICANT |
| Applicant returned to address corrections | 3/1/2022 | SELLA BENYAMIN |
| Plan Check Approved | 4/22/2022 | JON BLAINE |
| Issued | 4/22/2022 | APPLICANT |
| CofO in Progress | 11/7/2024 | MISAEL ESPARZA |
| No Progress | 11/15/2024 | MISAEL ESPARZA |
| CofO in Progress | 11/15/2024 | MISAEL ESPARZA |
| CofO in Progress | 11/15/2024 | MISAEL ESPARZA |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
| CofO Issued | 2/13/2025 | RUBEN SALAS |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 6/7/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/10/2021 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 7/28/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 10/3/2021 | JOHN CONNEALLY |
| ZI | Cleared | 10/26/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 2/9/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/16/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 8/3/2022 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 8/3/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/12/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 8/16/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/30/2022 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 8/31/2022 | Partial Approval | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/21/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 10/21/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 10/24/2022 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 10/27/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/27/2022 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/3/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 11/3/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/3/2022 | Partial Approval | MISAEL ESPARZA |
| Insulation | 11/17/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/23/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 11/23/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 11/23/2022 | Corrections Issued | MISAEL ESPARZA |
| MERV13>=Rough | 11/23/2022 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 11/23/2022 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 12/1/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 12/1/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 12/29/2022 | Approved | MISAEL ESPARZA |
| Insulation | 12/29/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/29/2022 | Partial Inspection | MISAEL ESPARZA |
| Insulation | 1/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/13/2023 | Conditional Approval | MISAEL ESPARZA |
| Insulation | 1/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 1/13/2023 | Approved | MISAEL ESPARZA |
| Insulation | 1/17/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/2/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/2/2023 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 2/6/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/16/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 2/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 2/24/2023 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 3/1/2023 | Approved | MISAEL ESPARZA |
| Sewer | 5/25/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 10/10/2023 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | MISAEL ESPARZA |
| Final | 10/16/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 10/16/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 10/16/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 10/16/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 10/16/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 11/21/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 11/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 11/21/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 11/21/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/11/2023 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Final | 12/11/2023 | No Access for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 12/11/2023 | No Access for Inspection | MISAEL ESPARZA |
| Service/Power Release | 12/11/2023 | No Access for Inspection | MISAEL ESPARZA |
| Sewer | 12/11/2023 | No Access for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 12/11/2023 | No Access for Inspection | MISAEL ESPARZA |
| Final | 5/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 5/16/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 5/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 5/16/2024 | Approved | MISAEL ESPARZA |
| Final | 7/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 7/9/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 7/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/19/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 8/19/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 10/18/2024 | No Access for Inspection | MISAEL ESPARZA |
| Service/Power Release | 10/18/2024 | No Access for Inspection | MISAEL ESPARZA |
| Final | 11/5/2024 | Corrections Issued | MISAEL ESPARZA |
| Service/Power Release | 11/5/2024 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 11/15/2024 | Corrections Issued | MISAEL ESPARZA |