5656 N CASE AVE 91601
Certificate Information: 5656 N CASE AVE 91601
- Application / Permit
- 21010-20000-02106
- Plan Check / Job No.
- B21VN05030
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 38'-8" X 26' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
- Permit Issued
- Issued on 11/12/2021
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/16/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 6/21/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/23/2021 | APPLICANT |
| Applicant returned to address corrections | 10/27/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 11/3/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 11/10/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 11/12/2021 | APPLICANT |
| CofO in Progress | 1/24/2023 | JUAN VALENZUELA |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
| CofO Issued | 1/24/2023 | MICHAEL SMITH |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/29/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/29/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 10/5/2021 | ANDRES COVARRUBIAS |
| Hydrant and Access approval | Cleared | 10/22/2021 | JOHN CONNEALLY |
| Address approval | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/27/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/11/2022 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/1/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/8/2022 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 6/8/2022 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 6/8/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 6/8/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/7/2022 | Approved | JOHN HAYES |
| Green Building Rough | 7/7/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/7/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | JOHN HAYES |
| Insulation | 7/20/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/20/2022 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 7/29/2022 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/29/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/22/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 9/15/2022 | Approved | DEANDRE HOFFMAN |
| Sewer | 9/15/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/10/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/23/2023 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 1/23/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/23/2023 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 1/23/2023 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 1/23/2023 | Approved | JUAN VALENZUELA |