839 N TOYOPA DR 90272
Certificate Information: 839 N TOYOPA DR 90272
- Application / Permit
- 21010-20000-02064
- Plan Check / Job No.
- B21VN04941
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 56'8" X 59'11" 2-STORY SFD WITH (2) CAR GARAGE AND (1) CAR GARAGE ATTACHED AND HABITABLE BASEMENT , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/1/2022
- Issuing Office
- Current Status
- CofO Issued on 9/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | RARES BODEA |
| Corrections Issued | 5/31/2021 | RARES BODEA |
| Quality Review Completed | 6/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Applicant returned to address corrections | 6/30/2021 | RARES BODEA |
| Applicant returned to address corrections | 7/8/2021 | RARES BODEA |
| Applicant returned to address corrections | 11/15/2021 | RARES BODEA |
| Applicant returned to address corrections | 12/15/2021 | RARES BODEA |
| Plan Check Approved | 1/3/2022 | RARES BODEA |
| Issued | 2/1/2022 | APPLICANT |
| CofO in Progress | 8/30/2023 | EVAN COOPER |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
| CofO Issued | 9/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | SAUL GARCIA |
| Permit | Cleared | 6/10/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 6/10/2021 | SAUL GARCIA |
| Trees in Parkway | Cleared | 7/1/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 7/29/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/29/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | SAUL GARCIA |
| Excavation more than 5-ft deep | Cleared | 11/15/2021 | CALOSHA APPROVED |
| Hold | Cleared | 12/14/2021 | JASON SHEETS |
| GPI Written Notices | Cleared | 12/15/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 12/15/2021 | RARES BODEA |
| Hold | Cleared | 2/9/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/14/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 3/22/2022 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 4/6/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 4/20/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 4/20/2022 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 5/4/2022 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/10/2022 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 5/10/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 5/11/2022 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | ANDREW NAVE |
| Wood Frame | 6/22/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 8/25/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Wood Construction | 8/26/2022 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 8/29/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 8/29/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 8/30/2022 | No Access for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/1/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 9/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 9/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 9/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 9/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 9/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/8/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 9/8/2022 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 9/13/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/21/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/27/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/27/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 9/27/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/7/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Insulation | 10/7/2022 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Partial Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 11/1/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Conditional Approval | ANDREW NAVE |
| HVAC-Rough | 11/1/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/1/2022 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 11/1/2022 | Approved | ANDREW NAVE |
| Wood Frame | 11/1/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 11/14/2022 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 11/14/2022 | Approved | BRENDAN LOONEY |
| Insulation | 11/14/2022 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/14/2022 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 11/14/2022 | Approved | BRENDAN LOONEY |
| Wood Frame | 11/14/2022 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 11/28/2022 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 11/28/2022 | Approved | KENNETH NAGLE |
| Drywall Nailing | 12/1/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 12/1/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/1/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/24/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Gas Test | 7/26/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 7/26/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/26/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 8/2/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 8/2/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 8/2/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 8/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 8/7/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 8/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 8/7/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 8/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 8/10/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 8/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 8/30/2023 | OK to Issue CofO | EVAN COOPER |