839 N TOYOPA DR 90272

Certificate Information: 839 N TOYOPA DR 90272

Application / Permit
21010-20000-02064
Plan Check / Job No.
B21VN04941
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 56'8" X 59'11" 2-STORY SFD WITH (2) CAR GARAGE AND (1) CAR GARAGE ATTACHED AND HABITABLE BASEMENT , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/1/2022
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 RARES BODEA
Corrections Issued 5/31/2021 RARES BODEA
Quality Review Completed 6/4/2021 STEVEN KIM
Building Plans Picked Up 6/7/2021 APPLICANT
Applicant returned to address corrections 6/30/2021 RARES BODEA
Applicant returned to address corrections 7/8/2021 RARES BODEA
Applicant returned to address corrections 11/15/2021 RARES BODEA
Applicant returned to address corrections 12/15/2021 RARES BODEA
Plan Check Approved 1/3/2022 RARES BODEA
Issued 2/1/2022 APPLICANT
CofO in Progress 8/30/2023 EVAN COOPER
Permit Finaled 9/12/2023 DANIEL ORRANTE
CofO Issued 9/12/2023 DANIEL ORRANTE
Permit Finaled 9/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/10/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 6/10/2021 SAUL GARCIA
Permit Cleared 6/10/2021 SAUL GARCIA
Sewer availability Cleared 6/10/2021 SAUL GARCIA
Trees in Parkway Cleared 7/1/2021 JOHN KIM
Hydrant and Access approval Cleared 7/29/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/29/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/29/2021 SAUL GARCIA
Excavation more than 5-ft deep Cleared 11/15/2021 CALOSHA APPROVED
Hold Cleared 12/14/2021 JASON SHEETS
GPI Written Notices Cleared 12/15/2021 RARES BODEA
Grading Pre-Inspection Cleared 12/15/2021 RARES BODEA
Hold Cleared 2/9/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2022 Approved ANDREW NAVE
Underground Mechanical 3/22/2022 Partial Approval ANDREW NAVE
Underground Mechanical 4/6/2022 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 4/20/2022 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 4/20/2022 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 4/22/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/3/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/4/2022 Approved MICHAEL PELHAM
Deputy Reinf. Concrete 5/10/2022 Approved ANDREW NAVE
Footing/Foundation/Slab 5/10/2022 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/11/2022 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval ANDREW NAVE
Wood Frame 6/22/2022 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval ANDREW NAVE
HVAC-Rough 8/25/2022 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 8/26/2022 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Corrections Issued BRENDAN LOONEY
Green Building Rough 8/29/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/29/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 8/30/2022 No Access for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 9/1/2022 Corrections Issued BRENDAN LOONEY
HVAC-Rough 9/1/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 9/1/2022 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 9/7/2022 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 9/7/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 9/7/2022 Not Ready for Inspection BRENDAN LOONEY
Shower Pan 9/7/2022 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 9/7/2022 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 9/8/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 9/8/2022 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Corrections Issued BRENDAN LOONEY
HVAC-Rough 9/13/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 9/21/2022 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Conditional Approval ANDREW NAVE
BUILDING-Rough-Frame 9/27/2022 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 9/27/2022 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 9/27/2022 Not Ready for Inspection KEVIN SARGSYAN
Verify Sprinkler Sign Off 9/27/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 10/7/2022 Corrections Issued BRENDAN LOONEY
Green Building Rough 10/7/2022 Not Ready for Inspection BRENDAN LOONEY
Insulation 10/7/2022 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 10/7/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Partial Inspection KENNETH NAGLE
ELECTRICAL-Rough 11/1/2022 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Conditional Approval ANDREW NAVE
HVAC-Rough 11/1/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 11/1/2022 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 11/1/2022 Approved ANDREW NAVE
Wood Frame 11/1/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 11/14/2022 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Approved BRENDAN LOONEY
HVAC-Rough 11/14/2022 Approved BRENDAN LOONEY
Insulation 11/14/2022 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 11/14/2022 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 11/14/2022 Approved BRENDAN LOONEY
Wood Frame 11/14/2022 Conditional Approval BRENDAN LOONEY
Drywall Nailing 11/28/2022 Partial Approval KENNETH NAGLE
Green Building Rough 11/28/2022 Approved KENNETH NAGLE
Drywall Nailing 12/1/2022 Approved KEVIN SARGSYAN
Insulation 12/1/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/1/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 7/24/2023 Corrections Issued OGANES TARAKHCHYAN
Gas Test 7/26/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Final 7/26/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 7/26/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Gas Test 8/2/2023 Approved STEPHANIE SWANSON
HVAC-Final 8/2/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 8/2/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 8/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 8/7/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 8/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
Service/Power Release 8/7/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 8/7/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 8/10/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Service/Power Release 8/10/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 8/30/2023 OK to Issue CofO EVAN COOPER