4448 N MORSE AVE 91604
Certificate Information: 4448 N MORSE AVE 91604
- Application / Permit
- 21010-20000-02055
- Plan Check / Job No.
- B21VN04936
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY (38'-0"x 54'-6") SFD W/ATT GARAGE W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/25/2021
- Issuing Office
- Current Status
- CofO Issued on 10/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | PETER MOSESIAN |
| Corrections Issued | 5/8/2021 | PETER MOSESIAN |
| Quality Review Completed | 5/12/2021 | OMID HEDAYAT |
| Plan Check Approved | 10/22/2021 | PETER MOSESIAN |
| Issued | 10/25/2021 | APPLICANT |
| CofO in Progress | 9/30/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
| CofO Issued | 10/14/2022 | DEROLD HAUFF |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 5/5/2021 | JASON SHEETS |
| Permit | Cleared | 6/7/2021 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 7/8/2021 | JOHN KIM |
| Sewer availability | Cleared | 8/11/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 8/13/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/17/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/28/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | CARLOS AGUILERA |
| ZI | Cleared | 10/14/2021 | DANG NGUYEN |
| Hold | Cleared | 11/8/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/10/2021 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/10/2021 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 11/10/2021 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/17/2021 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/27/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/27/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/27/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/3/2022 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 2/8/2022 | Corrections Issued | ARAM AVEDISIAN |
| Drywall Nailing | 2/16/2022 | Conditional Approval | CALEB MEISTER |
| Green Building Rough | 2/16/2022 | Conditional Approval | CALEB MEISTER |
| Shower Pan | 3/7/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/14/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/2/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 5/2/2022 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 5/2/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/2/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 9/2/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/2/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 9/2/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 9/2/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 9/2/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/2/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 9/2/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 9/8/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/8/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 9/8/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 9/8/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/22/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 9/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/22/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 9/30/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/30/2022 | Approved | CHRISTOPHE COCHRAN |