4199 E VERDANT ST 90039

Certificate Information: 4199 E VERDANT ST 90039

Application / Permit
21010-20000-02041
Plan Check / Job No.
B21VN04898
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 34'-1" X 19'-6", 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 COLIN LOREDO
Corrections Issued 6/2/2021 COLIN LOREDO
Quality Review Completed 6/8/2021 OMID HEDAYAT
Building Plans Picked Up 6/15/2021 APPLICANT
Applicant returned to address corrections 10/19/2021 COLIN LOREDO
Plan Check Approved 10/19/2021 COLIN LOREDO
No Progress 11/17/2021 COLIN LOREDO
Plan Check Approved 12/14/2021 COLIN LOREDO
Issued 12/14/2021 APPLICANT
CofO in Progress 7/11/2022 HAMIK HARTOUNIAN
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/9/2021 WALLIE JONG
ZI Cleared 8/10/2021 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 8/11/2021 WALLIE JONG
Sewer availability Cleared 8/25/2021 WALLIE JONG
Low Impact Development Cleared 9/24/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/29/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/17/2021 Partial Inspection HAMIK HARTOUNIAN
Posting Pre-Inspection 12/29/2021 Approved HAMIK HARTOUNIAN
Pre-Inspection 12/29/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/11/2022 Partial Inspection SCOTT FINNILA
Underground Mechanical 1/11/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 1/18/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/22/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/22/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 2/22/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/22/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 2/22/2022 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/28/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 2/28/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/10/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/10/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Approved HAMIK HARTOUNIAN
Insulation 3/17/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/17/2022 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 3/25/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 3/31/2022 Approved HAMIK HARTOUNIAN
Shower Pan 3/31/2022 Conditional Approval HAMIK HARTOUNIAN
Sewer 5/19/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 5/19/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 6/16/2022 Approved HAMIK HARTOUNIAN
Final 6/16/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 6/16/2022 Approved HAMIK HARTOUNIAN
HVAC-Final 6/16/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Final 6/16/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 6/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 6/16/2022 Approved HAMIK HARTOUNIAN
Final 7/11/2022 OK to Issue CofO HAMIK HARTOUNIAN
Service/Power Release 7/11/2022 Approved HAMIK HARTOUNIAN