22636 W CANTARA ST 91304

Certificate Information: 22636 W CANTARA ST 91304

Application / Permit
21010-20000-02036
Plan Check / Job No.
B21VN04867
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 25'-0" x 20'-0" DETACHED RECREATION ROOM PER DESIGN
Permit Issued
Issued on 1/13/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/10/2021 ALFRED RAMIREZ
Corrections Issued 5/12/2021 ALFRED RAMIREZ
Applicant returned to address corrections 1/12/2022 ALFRED RAMIREZ
Issued 1/13/2022 APPLICANT
Building Plans Picked Up 1/14/2022 APPLICANT
CofO in Progress 1/31/2025 CHRIS CHRISTENSEN
CofO Issued 2/10/2025 JOHN JANSON
Permit Finaled 2/10/2025 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 7/22/2021 RIDWAN HARDY
Low Impact Development Cleared 11/18/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 12/8/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/9/2021 CARLOS AGUILERA

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21243 VENTURA BLVD #115      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/27/2022 Approved DAVID SCANTLIN
Underground Mechanical 1/27/2022 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 1/31/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Approved PETER FOLLING
Wood Frame 3/4/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 3/15/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/15/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 3/15/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/15/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 3/15/2022 Corrections Issued CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 3/15/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 3/15/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/23/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/23/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 3/23/2022 Approved CHRIS CHRISTENSEN
Insulation 3/23/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/23/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 3/23/2022 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 3/23/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 4/6/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 12/18/2023 Approved CHRIS CHRISTENSEN
Final 12/18/2023 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/18/2023 Approved CHRIS CHRISTENSEN
Green Building Final 12/18/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 12/18/2023 Not Required CHRIS CHRISTENSEN
Smoke Detectors 12/18/2023 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 12/18/2023 Approved CHRIS CHRISTENSEN
Final 4/10/2024 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved CHRIS CHRISTENSEN
Final 1/30/2025 OK to Issue CofO CHRIS CHRISTENSEN