11571 W VALLEY SPRING LANE 91604
Certificate Information: 11571 W VALLEY SPRING LANE 91604
- Application / Permit
- 21010-20000-02026
- Plan Check / Job No.
- B21VN04848
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY 742 SQ. FT. ACCESSORY DWELLING UNIT AT THE REAR OF THE LOT PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2021 | JESSE ARELLANO |
| Corrections Issued | 4/30/2021 | JESSE ARELLANO |
| Issued | 10/6/2021 | APPLICANT |
| Building Plans Picked Up | 10/7/2021 | APPLICANT |
| CofO in Progress | 8/3/2022 | DAVID MATSON |
| CofO Issued | 8/23/2022 | MICHAEL SMITH |
| Permit Finaled | 8/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 9/24/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/27/2021 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 9/28/2021 | ABDULLAH SADOZAI |
| Green Code | Cleared | 10/6/2021 | JESSE ARELLANO |
Contact Information
| Contractor | South Land Remodeling Inc; Lic. No.: 901842-B | 10770 DES MOINES AVE NORTHRIDGE, CA 91326 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/23/2021 | Corrections Issued | MATT KELLERMAN |
| Footing/Foundation/Slab | 11/24/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/17/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/6/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/17/2022 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 2/17/2022 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 2/17/2022 | Approved | MATT KELLERMAN |
| HVAC-Rough | 2/17/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Rough | 2/17/2022 | Partial Approval | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 2/17/2022 | Approved | MATT KELLERMAN |
| Insulation | 2/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 3/4/2022 | Corrections Issued | THOMAS FINNILA |
| Insulation | 3/10/2022 | Approved | DAVID MATSON |
| Drywall Nailing | 3/15/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 3/29/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | DAVID MATSON |
| Final | 6/14/2022 | Corrections Issued | DAVID MATSON |
| Green Building Final | 6/14/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 6/14/2022 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 6/14/2022 | Approved | DAVID MATSON |
| Final | 7/7/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Service/Power Release | 7/7/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 8/2/2022 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 8/2/2022 | Approved | DAVID MATSON |