5116 N SOPHIA AVE 91436
Certificate Information: 5116 N SOPHIA AVE 91436
- Application / Permit
- 21010-20000-02011
- Plan Check / Job No.
- B21VN04823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- KEEP 1 SQFT OF FOOTING ON (E) SFD AND BUILD NEW 2-STORY (59'-0"x 55'-10") 4764 SQFT SFD W/ATT 342 SQFT GARAGE, W/NFPA 13D SPRINKLERS THROGUHOUT
- Permit Issued
- Issued on 9/16/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | PETER MOSESIAN |
| Corrections Issued | 5/30/2021 | PETER MOSESIAN |
| Quality Review Completed | 6/4/2021 | OMID HEDAYAT |
| Plan Check Approved | 9/16/2021 | PETER MOSESIAN |
| Issued | 9/16/2021 | APPLICANT |
| CofO in Progress | 11/2/2023 | VINCENT HANLEY |
| CofO Issued | 11/22/2023 | JOHN JANSON |
| Permit Finaled | 11/22/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/2/2021 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 6/7/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 7/23/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 9/3/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/7/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/16/2021 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/7/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 1/19/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 2/18/2022 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/23/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/23/2022 | Approved | VINCENT HANLEY |
| Insulation | 7/1/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/8/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/8/2022 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/15/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 9/15/2022 | Approved | JESUS PINEDA |
| Shower Pan | 9/15/2022 | Approved | VINCENT HANLEY |
| Final | 9/15/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 9/15/2023 | Approved | VINCENT HANLEY |
| MERV13>=Final | 9/15/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 9/15/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 9/15/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 11/1/2023 | Approved | VINCENT HANLEY |
| Final | 11/1/2023 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 11/1/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/1/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | VINCENT HANLEY |