10013 N SILVERTON AVE 91042

Certificate Information: 10013 N SILVERTON AVE 91042

Application / Permit
21010-20000-01938
Plan Check / Job No.
B21VN04724
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1 STORY SINGLE FAMILY DWELLING (65'-2"x 49'-2"), 2138 SQFT W/ATTACHED 390 SQFT 2-CAR GARAGE W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 11/27/2024
Issuing Office
Metro
Current Status
Issued on 11/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/26/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 PETER MOSESIAN
Corrections Issued 5/29/2021 PETER MOSESIAN
Quality Review Completed 6/1/2021 OMID HEDAYAT
Plan Check Approved 11/14/2024 PETER MOSESIAN
Issued 11/27/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/30/2021 GABRIEL ROBLES
Address approval Cleared 4/7/2022 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 4/23/2022 STEVEN WECHSLER
Hydrant and Access approval Cleared 4/25/2022 CINDY JOSSELYN
Private sewage disp. approval Cleared 3/13/2024 DAN RYAN EVANGELISTA
Low Impact Development Cleared 7/21/2024 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 7/30/2024 LEE GUILBEAUX
Trees in Parkway Cleared 10/21/2024 MIGUEL ORNELAS
Trees in Parkway Cleared 10/21/2024 MIGUEL ORNELAS
Grading Pre-Inspection Cleared 10/28/2024 PETER MOSESIAN
Specific Plan Cleared 10/31/2024 ERICK MARCHENA
Specific Plan Cleared 10/31/2024 ERICK MARCHENA
Permit Cleared 11/12/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/26/2024 Partial Inspection WILLIAM WREN
Footing/Foundation/Slab 3/3/2025 Corrections Issued WILLIAM WREN
PLUMBING-Rough 3/3/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 3/6/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 3/18/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/7/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/23/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 6/23/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 6/23/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 9/5/2025 Partial Inspection WILLIAM WREN
ELECTRICAL-Rough 10/7/2025 Partial Inspection KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 12/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 12/9/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 12/9/2025 Approved NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 12/9/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 1/2/2026 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 1/8/2026 Approved NICHOLAS TROWBRIDGE
Green Building Rough 1/8/2026 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 1/8/2026 Approved NICHOLAS TROWBRIDGE
Insulation 1/16/2026 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 2/2/2026 Approved NICHOLAS TROWBRIDGE