6958 N FORBES AVE 91406

Certificate Information: 6958 N FORBES AVE 91406

Application / Permit
21010-20000-01934
Plan Check / Job No.
B21VN04718
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23' 9" X 21' 1-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK DONE PER WFPP. SEE COMMENTS
Permit Issued
Issued on 12/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/26/2021 PARISA ZAHABI
Corrections Issued 4/27/2021 PARISA ZAHABI
Plan Check Approved 3/25/2022 GURUNATH NESARAJAH
Building Plans Picked Up 3/30/2022 APPLICANT
Issued 12/29/2022 APPLICANT
CofO in Progress 4/16/2024 RAUL OLAGI
Permit Finaled 5/3/2024 RUBEN SALAS
CofO Issued 5/3/2024 RUBEN SALAS
Permit Finaled 5/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/8/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 7/30/2021 MATTHEW CRAIG
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Low Impact Development Cleared 3/3/2022 TA ANH
Roof/Waste drainage to street Cleared 3/4/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/11/2022 ABDULLAH SADOZAI
Sewer availability Cleared 3/11/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/4/2023 Approved RAUL OLAGI
Sewer 2/28/2023 Approved RAUL OLAGI
PLUMBING-Rough 4/3/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 4/7/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/1/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 8/1/2023 Corrections Issued RAUL OLAGI
Green Building Rough 8/1/2023 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 8/1/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/1/2023 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 8/1/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 8/9/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 8/14/2023 Approved RAUL OLAGI
Green Building Rough 8/14/2023 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 8/14/2023 Approved RAUL OLAGI
Shower Pan 8/14/2023 Approved RAUL OLAGI
Insulation 8/16/2023 Approved RAUL OLAGI
Drywall Nailing 8/18/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/18/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/22/2023 Approved RAUL OLAGI
ELECTRICAL-Final 12/4/2023 Corrections Issued RAUL OLAGI
Final 12/4/2023 Corrections Issued RAUL OLAGI
HVAC-Final 12/4/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 12/4/2023 Corrections Issued RAUL OLAGI
Service/Power Release 12/4/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Final 2/13/2024 Corrections Issued RAUL OLAGI
Final 4/2/2024 Partial Inspection JOHN COLEMAN
Green Building Final 4/2/2024 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Not Ready JOHN COLEMAN
Service/Power Release 4/2/2024 Not Ready for Inspection JOHN COLEMAN
Smoke Detectors 4/2/2024 Approved JOHN COLEMAN
Final 4/3/2024 Not Ready for Inspection JOHN COLEMAN
HVAC-Final 4/3/2024 Approved JOHN COLEMAN
PLUMBING-Final 4/3/2024 Not Ready for Inspection JOHN COLEMAN
Service/Power Release 4/3/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Final 4/15/2024 Approved RAUL OLAGI
Final 4/15/2024 OK to Issue CofO RAUL OLAGI
PLUMBING-Final 4/15/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Approved RAUL OLAGI
Service/Power Release 4/15/2024 Approved RAUL OLAGI