6958 N FORBES AVE 91406
Certificate Information: 6958 N FORBES AVE 91406
- Application / Permit
- 21010-20000-01934
- Plan Check / Job No.
- B21VN04718
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23' 9" X 21' 1-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK DONE PER WFPP. SEE COMMENTS
- Permit Issued
- Issued on 12/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2021 | PARISA ZAHABI |
| Corrections Issued | 4/27/2021 | PARISA ZAHABI |
| Plan Check Approved | 3/25/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Issued | 12/29/2022 | APPLICANT |
| CofO in Progress | 4/16/2024 | RAUL OLAGI |
| Permit Finaled | 5/3/2024 | RUBEN SALAS |
| CofO Issued | 5/3/2024 | RUBEN SALAS |
| Permit Finaled | 5/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 7/30/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/4/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2022 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 3/11/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2023 | Approved | RAUL OLAGI |
| Sewer | 2/28/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 4/3/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 4/7/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/1/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/1/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 8/1/2023 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 8/1/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/1/2023 | Corrections Issued | RAUL OLAGI |
| Verify Sprinkler Sign Off | 8/1/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 8/9/2023 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/14/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 8/14/2023 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 8/14/2023 | Approved | RAUL OLAGI |
| Shower Pan | 8/14/2023 | Approved | RAUL OLAGI |
| Insulation | 8/16/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 8/18/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/18/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/22/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/4/2023 | Corrections Issued | RAUL OLAGI |
| Final | 12/4/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 12/4/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 12/4/2023 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 12/4/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 2/13/2024 | Corrections Issued | RAUL OLAGI |
| Final | 4/2/2024 | Partial Inspection | JOHN COLEMAN |
| Green Building Final | 4/2/2024 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Not Ready | JOHN COLEMAN |
| Service/Power Release | 4/2/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 4/2/2024 | Approved | JOHN COLEMAN |
| Final | 4/3/2024 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Final | 4/3/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 4/3/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 4/3/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Final | 4/15/2024 | Approved | RAUL OLAGI |
| Final | 4/15/2024 | OK to Issue CofO | RAUL OLAGI |
| PLUMBING-Final | 4/15/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 4/15/2024 | Approved | RAUL OLAGI |