20510 W OVERLOOK CT 91326

Certificate Information: 20510 W OVERLOOK CT 91326

Application / Permit
21010-20000-01916
Plan Check / Job No.
B21VN04689
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE PLAN 5AR W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/28/2022
Issuing Office
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 ALYSSA N NARCISO
Corrections Issued 6/2/2021 ALYSSA N NARCISO
Quality Review Completed 6/4/2021 STEVEN KIM
Building Plans Picked Up 6/18/2021 APPLICANT
Plan Check Approved 3/25/2022 PETER MOSESIAN
Issued 3/28/2022 APPLICANT
CofO in Progress 4/14/2023 HENRY KIM
Permit Finaled 4/14/2023 MICHAEL SMITH
CofO Issued 4/14/2023 MICHAEL SMITH
Permit Finaled 4/14/2023 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 11/9/2021 DANG NGUYEN
CPC Cleared 11/9/2021 DANG NGUYEN
Specific Plan Cleared 11/9/2021 DANG NGUYEN
Tract Map conditions Cleared 11/9/2021 DANG NGUYEN
Tract Map conditions Cleared 11/9/2021 DANG NGUYEN
ZA Case Cleared 11/9/2021 DANG NGUYEN
ZA Case Cleared 11/9/2021 DANG NGUYEN
Address approval Cleared 11/10/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/10/2021 LEE GUILBEAUX
Permit Cleared 11/10/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/10/2021 LEE GUILBEAUX
Sewer availability Cleared 11/10/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/10/2021 LEE GUILBEAUX
Low Impact Development Cleared 12/16/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 3/4/2022 JOHN CONNEALLY
Grading Pre-Inspection Cleared 3/23/2022 ALYSSA N NARCISO

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Braatz,, Tara Elizabeth; Lic. No.: C79028 24855 CALLE CARMEL      LAGUNA HILLS, CA 92653

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/11/2022 Partial Approval HENRY KIM
Footing/Foundation/Slab 6/14/2022 Approved HENRY KIM
Deputy Reinf. Concrete 6/15/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval SEAN WIRCH
Sewer 9/14/2022 Corrections Issued HENRY KIM
Sewer 9/16/2022 Approved HENRY KIM
Underground Mechanical 9/30/2022 Approved HENRY KIM
Deputy Other (see comments) 10/5/2022 Conditional Approval HENRY KIM
Deputy Wood Construction 10/25/2022 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 12/5/2022 Approved HENRY KIM
Green Building Rough 12/5/2022 Corrections Issued HENRY KIM
HVAC-Rough 12/5/2022 Approved HENRY KIM
Interior/Exterior Lathing 12/5/2022 Partial Approval HENRY KIM
PLUMBING-Rough 12/5/2022 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 12/5/2022 Approved HENRY KIM
BUILDING-Rough-Frame 12/7/2022 Not Ready for Inspection JEFFREY PARD
Green Building Rough 12/7/2022 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 12/7/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 12/7/2022 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval JEFFREY PARD
PLUMBING-Rough 12/9/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/16/2022 Not Ready for Inspection HENRY KIM
Drywall Nailing 12/16/2022 Approved HENRY KIM
Green Building Rough 12/16/2022 Approved HENRY KIM
Interior/Exterior Lathing 12/16/2022 Approved HENRY KIM
Gas Test 1/23/2023 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Approved HENRY KIM
Service/Power Release 2/1/2023 Not Ready for Inspection HENRY KIM
Service/Power Release 2/9/2023 Approved HENRY KIM
Gas Test 2/16/2023 Approved HENRY KIM
Special/Order Compliance 2/22/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 2/23/2023 Approved JEFFREY PARD
Drywall Nailing 2/27/2023 Approved HENRY KIM
Verify Sprinkler Sign Off 2/27/2023 Corrections Issued HENRY KIM
ELECTRICAL-Final 3/31/2023 Corrections Issued HENRY KIM
HVAC-Final 3/31/2023 Corrections Issued HENRY KIM
PLUMBING-Final 3/31/2023 Approved HENRY KIM
BUILDING-Rough-Frame 4/12/2023 Approved HENRY KIM
ELECTRICAL-Final 4/12/2023 Approved HENRY KIM
Final 4/12/2023 Not Ready for Inspection HENRY KIM
Green Building Final 4/12/2023 Approved HENRY KIM
HVAC-Final 4/12/2023 Corrections Issued HENRY KIM
Smoke Detectors 4/12/2023 Approved HENRY KIM
Verify Sprinkler Sign Off 4/12/2023 Approved HENRY KIM
Final 4/13/2023 OK to Issue CofO HENRY KIM
HVAC-Final 4/13/2023 Approved HENRY KIM