20519 W OVERLOOK CT 91326

Certificate Information: 20519 W OVERLOOK CT 91326

Application / Permit
21010-20000-01912
Plan Check / Job No.
B21VN04689
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 3/28/2022
Issuing Office
Current Status
CofO Issued on 5/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 ALYSSA N NARCISO
Corrections Issued 6/2/2021 ALYSSA N NARCISO
Quality Review Completed 6/4/2021 STEVEN KIM
Building Plans Picked Up 6/18/2021 APPLICANT
Plan Check Approved 3/25/2022 PETER MOSESIAN
Issued 3/28/2022 APPLICANT
CofO in Progress 5/20/2023 HENRY KIM
Permit Finaled 5/22/2023 MICHAEL SMITH
CofO Issued 5/22/2023 MICHAEL SMITH
Permit Finaled 5/22/2023 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 11/9/2021 DANG NGUYEN
CPC Cleared 11/9/2021 DANG NGUYEN
Specific Plan Cleared 11/9/2021 DANG NGUYEN
Tract Map conditions Cleared 11/9/2021 DANG NGUYEN
Tract Map conditions Cleared 11/9/2021 DANG NGUYEN
ZA Case Cleared 11/9/2021 DANG NGUYEN
ZA Case Cleared 11/9/2021 DANG NGUYEN
Address approval Cleared 11/10/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/10/2021 LEE GUILBEAUX
Permit Cleared 11/10/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/10/2021 LEE GUILBEAUX
Sewer availability Cleared 11/10/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/10/2021 LEE GUILBEAUX
Low Impact Development Cleared 12/16/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 3/4/2022 JOHN CONNEALLY
Grading Pre-Inspection Cleared 3/23/2022 ALYSSA N NARCISO

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Braatz,, Tara Elizabeth; Lic. No.: C79028 24855 CALLE CARMEL      LAGUNA HILLS, CA 92653

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/17/2022 Not Ready for Inspection HENRY KIM
Underground Mechanical 5/25/2022 Approved SEAN WIRCH
Footing/Foundation/Slab 6/16/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Corrections Issued JUSTIN HAWLEY
Sewer 9/14/2022 Corrections Issued HENRY KIM
Sewer 9/16/2022 Approved HENRY KIM
Underground Mechanical 9/30/2022 Approved HENRY KIM
Deputy Wood Construction 10/31/2022 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval HENRY KIM
Interior/Exterior Lathing 12/20/2022 Partial Approval HENRY KIM
BUILDING-Rough-Frame 1/11/2023 Approved HENRY KIM
ELECTRICAL-Rough 1/11/2023 Approved HENRY KIM
Green Building Rough 1/11/2023 Approved HENRY KIM
HVAC-Rough 1/11/2023 Approved HENRY KIM
PLUMBING-Rough 1/11/2023 Approved HENRY KIM
Pre-Inspection 1/11/2023 Partial Inspection JUSTIN HAWLEY
Smoke Detectors 1/11/2023 Corrections Issued HENRY KIM
Special/Order Compliance 1/11/2023 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 1/11/2023 Approved HENRY KIM
Drywall Nailing 1/20/2023 Not Ready for Inspection HENRY KIM
Drywall Nailing 1/23/2023 Approved HENRY KIM
Interior/Exterior Lathing 1/23/2023 Approved HENRY KIM
Gas Test 3/1/2023 Not Ready for Inspection HENRY KIM
Gas Test 3/2/2023 Approved HENRY KIM
Special/Order Compliance 3/2/2023 Partial Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved HENRY KIM
Service/Power Release 3/10/2023 Corrections Issued HENRY KIM
Service/Power Release 3/14/2023 Approved HENRY KIM
Special/Order Compliance 3/14/2023 Partial Inspection MORRIS JACKSON
ELECTRICAL-Final 5/4/2023 Approved HENRY KIM
HVAC-Final 5/4/2023 Corrections Issued HENRY KIM
PLUMBING-Final 5/4/2023 Corrections Issued HENRY KIM
ELECTRICAL-Final 5/11/2023 Approved HENRY KIM
Final 5/11/2023 Corrections Issued HENRY KIM
Green Building Final 5/11/2023 Approved HENRY KIM
HVAC-Final 5/11/2023 Corrections Issued HENRY KIM
MERV13>=Final 5/11/2023 Approved HENRY KIM
PLUMBING-Final 5/11/2023 Corrections Issued HENRY KIM
ELECTRICAL-Final 5/15/2023 Approved HENRY KIM
Final 5/15/2023 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Approved HENRY KIM
HVAC-Final 5/15/2023 Approved HENRY KIM
PLUMBING-Final 5/15/2023 Approved HENRY KIM
Smoke Detectors 5/15/2023 Approved HENRY KIM
ELECTRICAL-Final 5/19/2023 Approved HENRY KIM
Final 5/19/2023 OK to Issue CofO HENRY KIM
HVAC-Final 5/19/2023 Approved HENRY KIM
PLUMBING-Final 5/19/2023 Approved HENRY KIM