2036 S CURSON AVE 90016
Certificate Information: 2036 S CURSON AVE 90016
- Application / Permit
- 21010-20000-01881
- Plan Check / Job No.
- B21VN04553
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 32'-0" x 35'-0" THREE-STORY SINGLE FAMILY DWELLING W/ ATT GARAGE (PARCEL A) AND ROOF DECK; NFPA-13D THRU-OUT. SMALL LOT SUBDIVISION PERSUANT TO TENTATIVE TRACT MAP NO. AA-2020-6489-PMLA-SL-HCA-1A. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN APPROVED.
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | SEAN SHAHMIRI |
| Corrections Issued | 5/26/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 6/10/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| Applicant returned to address corrections | 9/22/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 10/27/2022 | SEAN SHAHMIRI |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 1/24/2024 | SCOTT FINNILA |
| Permit Finaled | 1/27/2024 | DEROLD HAUFF |
| Permit Finaled | 1/27/2024 | DEROLD HAUFF |
| CofO Issued | 1/27/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | WALLIE JONG |
| Highway dedication | Cleared | 12/7/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | WALLIE JONG |
| Sewer availability | Cleared | 1/12/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 6/9/2022 | RIDWAN HARDY |
| "Q" conditions | Cleared | 8/4/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 8/4/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 8/5/2022 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 8/8/2022 | KURT CORRAL |
| Building over 36-ft | Cleared | 8/17/2022 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 9/8/2022 | ANDRES COVARRUBIAS |
| Miscellaneous | Cleared | 9/13/2022 | TERRY PHAN |
| Roof/Waste drainage to street | Cleared | 9/13/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ali, J Basma; Lic. No.: C53080 | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2023 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 4/6/2023 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | No Access for Inspection | JOSE AVILA |
| Deputy Steel/Welding | 4/17/2023 | Conditional Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/18/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 5/31/2023 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/22/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/22/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 7/3/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 7/3/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Conditional Approval | JOSE AVILA |
| HVAC-Rough | 7/12/2023 | Approved | JOSE AVILA |
| Shower Pan | 7/13/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | JOSE AVILA |
| Green Building Rough | 7/19/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 7/19/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/26/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/1/2023 | Partial Approval | JOSE AVILA |
| Insulation | 8/3/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/3/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/7/2023 | Not Ready for Inspection | JOSE AVILA |
| Drywall Nailing | 8/14/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/18/2023 | Approved | JOSE AVILA |
| Verify Rec and Parks Fee Memo | 10/13/2023 | Partial Approval | RONNIE MINDANAO |
| HVAC-Final | 10/18/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 11/1/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 11/13/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 11/15/2023 | Approved | MICHAEL LEWIS |
| Gas Test | 11/22/2023 | Approved | DAVID FEILER |
| PLUMBING-Final | 11/22/2023 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | DAVID FEILER |
| Verify Rec and Parks Fee Memo | 11/29/2023 | Approved | JOSE AVILA |
| Service/Power Release | 12/1/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Drywall Nailing | 1/4/2024 | No Access for Inspection | RONNIE MINDANAO |
| Final | 1/4/2024 | No Access for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/4/2024 | No Access for Inspection | RONNIE MINDANAO |
| Green Building Final | 1/4/2024 | No Access for Inspection | RONNIE MINDANAO |
| Service/Power Release | 1/4/2024 | No Access for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 1/4/2024 | No Access for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 1/9/2024 | Approved | RONNIE MINDANAO |
| Smoke Detectors | 1/9/2024 | Approved | RONNIE MINDANAO |
| Service/Power Release | 1/10/2024 | Approved | SCOTT FINNILA |
| Special/Order Compliance | 1/10/2024 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 1/23/2024 | Approved | SCOTT FINNILA |
| Final | 1/23/2024 | OK to Issue CofO | SCOTT FINNILA |
| Footing/Foundation/Slab | 1/23/2024 | Approved | SCOTT FINNILA |
| Green Building Final | 1/23/2024 | Approved | SCOTT FINNILA |