11310-11312 W OXNARD ST 91606

Certificate Information: 11310-11312 W OXNARD ST 91606

Application / Permit
21010-20000-01838
Plan Check / Job No.
B21VN04414
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION OF AN IRREGULAR 49'-2" X 33'-9", 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR CARPORT TO THE (E) SINGLE FAMILY DWELLING TO BECOME A DUPLEX. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 7/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 COLIN LOREDO
Corrections Issued 5/27/2021 COLIN LOREDO
Quality Review Completed 6/8/2021 OMID HEDAYAT
Building Plans Picked Up 6/15/2021 APPLICANT
Applicant returned to address corrections 11/22/2021 COLIN LOREDO
Plan Check Approved 11/30/2021 COLIN LOREDO
Issued 12/14/2021 APPLICANT
CofO in Progress 6/27/2022 JOHN HAYES
Permit Finaled 7/30/2022 DEROLD HAUFF
CofO Issued 7/30/2022 DEROLD HAUFF
Permit Finaled 7/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2021 GABRIEL ROBLES
Sewer availability Cleared 9/10/2021 GABRIEL ROBLES
Street width determination Cleared 9/10/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/13/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/14/2021 CHRIS VONG
Frnt yard landscape/Water mgmt Cleared 10/21/2021 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 10/29/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/21/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 1/19/2022 Corrections Issued MISAEL ESPARZA
Gas Test 1/19/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 1/21/2022 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 1/28/2022 Approved MATT KELLERMAN
BUILDING-Rough-Frame 3/9/2022 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Approved MATT KELLERMAN
Green Building Rough 3/9/2022 Approved MATT KELLERMAN
BUILDING-Rough-Frame 4/4/2022 Approved JACK KARGODORIAN
ELECTRICAL-Rough 4/4/2022 Approved JACK KARGODORIAN
HVAC-Rough 4/4/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 4/4/2022 Approved JACK KARGODORIAN
Insulation 4/11/2022 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 4/11/2022 Approved CALEB MEISTER
Insulation 4/14/2022 Approved CALEB MEISTER
Drywall Nailing 4/19/2022 Approved CALEB MEISTER
Gas Test 4/25/2022 Approved CALEB MEISTER
ELECTRICAL-Rough 5/18/2022 Partial Approval MATT KELLERMAN
Final 6/6/2022 Corrections Issued MATT KELLERMAN
Green Building Final 6/6/2022 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 6/6/2022 Approved MATT KELLERMAN
ELECTRICAL-Final 6/22/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Final 6/22/2022 Off-Hour Fees Due
Final 6/24/2022 OK to Issue CofO JOHN HAYES
Green Building Final 6/24/2022 Approved JOHN HAYES