607-607 1/2 W 41ST PL 90037
Certificate Information: 607-607 1/2 W 41ST PL 90037
- Application / Permit
- 21010-20000-01824
- Plan Check / Job No.
- B21VN04361
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY, 32'x36' DUPLEX WITH ATTACHED GARAGE. NFPA 13 D FIRE SPRINKLERS REQUIRED FRONT BLDG
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | ALYSSA N NARCISO |
| Corrections Issued | 5/24/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 5/27/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| Applicant returned to address corrections | 12/29/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/3/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 4/12/2022 | SEAN SHAHMIRI |
| Issued | 5/5/2022 | APPLICANT |
| CofO in Progress | 2/2/2024 | SABAS ALONSO |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2021 | STEVE MELGAR |
| Highway dedication | Cleared | 8/31/2021 | STEVE MELGAR |
| ZA Case | Cleared | 11/19/2021 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 12/8/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 12/9/2021 | RUEL COLE |
| Frnt yard landscape/Water mgmt | Cleared | 12/22/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 3/30/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/1/2022 | STEVE MELGAR |
| Hold | Cleared | 5/16/2022 | JASON SHEETS |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 14263 VALLEY VISTA BLVD. SHERMAN OAKS, CA 91403 |
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 5/23/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/31/2022 | Approved | HORACE FULTZ |
| Deputy Reinf. Concrete | 6/1/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | HORACE FULTZ |
| Deputy Wood Construction | 7/6/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/27/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/2/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 2/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 2/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 2/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/16/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 3/28/2023 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 3/28/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/28/2023 | Approved | SABAS ALONSO |
| Insulation | 12/18/2023 | Corrections Issued | SABAS ALONSO |
| Final | 12/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 12/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| MERV13>=Final | 12/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 12/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 12/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 1/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/14/2024 | Off-Hour Fees Due | |
| HVAC-Final | 1/14/2024 | Off-Hour Fees Due | |
| PLUMBING-Final | 1/14/2024 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 1/25/2024 | Approved | SABAS ALONSO |
| Final | 1/25/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/25/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 1/25/2024 | Approved | SABAS ALONSO |
| MERV13>=Final | 1/25/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/25/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 1/25/2024 | Approved | SABAS ALONSO |
| Smoke Detectors | 1/25/2024 | Approved | SABAS ALONSO |
| Final | 2/1/2024 | OK to Issue CofO | SABAS ALONSO |