966 N STONE CANYON ROAD 90077

Certificate Information: 966 N STONE CANYON ROAD 90077

Application / Permit
21010-20000-01814
Plan Check / Job No.
B21VN04343
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED 3-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 4/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 NILOOFAR MEHRAIN
Corrections Issued 4/17/2021 NILOOFAR MEHRAIN
Quality Review Completed 4/21/2021 CHON CHIO KUO
Applicant returned to address corrections 6/4/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/29/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/11/2021 NILOOFAR MEHRAIN
Plan Check Approved 3/29/2022 NILOOFAR MEHRAIN
Issued 4/4/2022 APPLICANT
CofO in Progress 5/21/2025 CHRISTOPHER WILSON
Permit Finaled 5/27/2025 RICHARD STEINBACH
CofO Issued 5/27/2025 RICHARD STEINBACH
Permit Finaled 5/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 4/28/2021 ANACANY HURTADO
Address approval Cleared 5/5/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 5/5/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 5/5/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 5/5/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 5/5/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 5/5/2021 SAUL GARCIA
Permit Cleared 5/5/2021 SAUL GARCIA
Street Frontage Cleared 5/5/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 5/10/2021 SAUL GARCIA
Sewer availability Cleared 5/10/2021 SAUL GARCIA
Trees in Parkway Cleared 5/20/2021 JOHN KIM
Hydrant and Access approval Cleared 5/26/2021 ROBERT DUFF
GPI Written Notices Cleared 6/4/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 6/4/2021 NILOOFAR MEHRAIN
Low Impact Development Cleared 6/23/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/24/2021 TRACY TATE
Flood clearance Cleared 3/17/2022 TIFFANY WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/27/2023 Conditional Approval CHRISTOPHER WILSON
FLOOD-Elevation Certificate 1/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 1/27/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/31/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 1/31/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 2/2/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 2/6/2023 Conditional Approval CHRISTOPHER WILSON
Deputy Other (see comments) 4/7/2023 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/10/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/10/2023 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/11/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/14/2023 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/17/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/19/2023 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 5/11/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/11/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/15/2023 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/14/2023 Conditional Approval CHRISTOPHER WILSON
FLOOD-Elevation Certificate 6/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/16/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 6/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/17/2023 Off-Hour Fees Due
Deputy Reinf. Concrete 6/21/2023 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/21/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/22/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/22/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/23/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/23/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/28/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 6/29/2023 Conditional Approval MICHAEL PELHAM
Underground Mechanical 7/12/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/19/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/21/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 7/26/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/26/2023 Approved CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/1/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 8/4/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 8/18/2023 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Conditional Approval CHRISTOPHER WILSON
Deputy Wood Construction 10/10/2023 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 10/16/2023 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/2/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 11/14/2023 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 11/14/2023 Not Ready for Inspection CHRISTOPHER WILSON
Gas Test 11/14/2023 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 11/14/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 11/14/2023 Approved CHRISTOPHER WILSON
PLUMBING-Rough 11/14/2023 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 11/14/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 11/28/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 11/30/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 12/6/2023 Approved CHRISTOPHER WILSON
PLUMBING-Rough 12/6/2023 Approved CHRISTOPHER WILSON
Shower Pan 12/6/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/13/2023 Partial Approval CHRISTOPHER WILSON
Insulation 12/13/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 12/21/2023 Partial Approval CHRISTOPHER WILSON
Shower Pan 12/21/2023 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/27/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/2/2024 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 1/2/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 1/2/2024 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 1/2/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 1/3/2024 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 1/12/2024 Conditional Approval STEPHANIE SWANSON
Interior/Exterior Lathing 1/12/2024 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 1/17/2024 Corrections Issued CHRISTOPHER WILSON
FLOOD-Proofing Certificate 1/17/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 1/17/2024 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 1/17/2024 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/19/2024 Partial Approval CHRISTOPHER WILSON
Insulation 1/19/2024 Approved CHRISTOPHER WILSON
Special/Order Compliance 1/19/2024 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/22/2024 Not Ready for Inspection MICHAEL PELHAM
FLOOD-Proofing Certificate 1/22/2024 Not Ready for Inspection MICHAEL PELHAM
Green Building Rough 1/22/2024 Not Ready for Inspection MICHAEL PELHAM
Special/Order Compliance 1/26/2024 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/31/2024 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 1/31/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 1/31/2024 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 2/12/2024 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/15/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 2/15/2024 Partial Approval CHRISTOPHER WILSON
Green Building Rough 2/15/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 2/26/2024 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 3/7/2024 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/13/2024 Partial Approval CHRISTOPHER WILSON
Sewer 3/14/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 4/12/2024 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 4/23/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/7/2024 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 5/9/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/23/2024 Approved CHRISTOPHER WILSON
Structural Steel Frame 6/7/2024 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/18/2024 Corrections Issued CHRISTOPHER WILSON
Gas Test 7/2/2024 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 7/2/2024 Partial Approval CHRISTOPHER WILSON
Insulation 7/24/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/5/2024 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 8/9/2024 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/12/2024 Partial Approval SEAN HAUPT
Reinforced Masonry Frame 8/22/2024 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/16/2024 Approved CHRISTOPHER WILSON
Pre-Inspection 9/25/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 9/30/2024 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 10/3/2024 Partial Approval CHRISTOPHER WILSON
Service/Power Release 10/15/2024 Approved CHRISTOPHER WILSON
Pre-Inspection 11/1/2024 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 11/22/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 11/25/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 1/10/2025 Approved CARLOS MATAMOROS
Gas Test 1/28/2025 Approved CHRISTOPHER WILSON
HVAC-Final 2/10/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Ready CHRISTOPHER WILSON
Pre-Inspection 5/16/2025 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/20/2025 Approved CHRISTOPHER WILSON
FLOOD-Elevation Certificate 5/20/2025 Approved CHRISTOPHER WILSON
FLOOD-Proofing Certificate 5/20/2025 Approved CHRISTOPHER WILSON
Final 5/20/2025 OK to Issue CofO CHRISTOPHER WILSON
Footing/Foundation/Slab 5/20/2025 Approved CHRISTOPHER WILSON
Green Building Final 5/20/2025 Approved CHRISTOPHER WILSON
Green Building Rough 5/20/2025 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 5/20/2025 Approved CHRISTOPHER WILSON