7655 W CURSON TER 90046

Certificate Information: 7655 W CURSON TER 90046

Application / Permit
21010-20000-01746
Plan Check / Job No.
B21VN04263
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
(N) IRREGULAR SHAPE 18'-0 X 8'-6.5" ELECTRICAL ROOM AND STORAGE ROOM BUILDING ACCESSORY TO SINGLE FAMILY DWELLING.
Permit Issued
Issued on 5/28/2024
Issuing Office
Valley
Current Status
Issued on 5/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/14/2021 APPLICANT
Assigned to Plan Check Engineer 4/20/2021 JESSE ARELLANO
Corrections Issued 4/21/2021 JESSE ARELLANO
Applicant returned to address corrections 7/28/2021 JESSE ARELLANO
Building Plans Picked Up 7/29/2021 APPLICANT
Applicant returned to address corrections 5/1/2024 JESSE ARELLANO
Applicant returned to address corrections 5/23/2024 JESSE ARELLANO
Issued 5/28/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/4/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/5/2022 AMAAN MALIK
Green Code Cleared 5/23/2024 JESSE ARELLANO

Contact Information

Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049

Inspector Information

BRIAN SULLIVAN, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/15/2024 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 8/22/2024 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/9/2024 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 9/20/2024 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 9/30/2024 Approved BRIAN SULLIVAN
Reinforced Concrete Frame 10/7/2024 Partial Approval BRIAN SULLIVAN
Reinforced Concrete Frame 10/22/2024 Approved BRIAN SULLIVAN
Deputy Wood Construction 11/18/2024 Conditional Approval BRIAN SULLIVAN
Wood Frame 11/19/2024 Approved BRIAN SULLIVAN
Drywall Nailing 11/26/2024 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 11/26/2024 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/14/2025 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 3/14/2025 Partial Approval CRAIG VAUGHAN