12508 N SADDLE CT 91326
Certificate Information: 12508 N SADDLE CT 91326
- Application / Permit
- 21010-20000-01744
- Plan Check / Job No.
- B21VN04252
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #654 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/18/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/18/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 5/21/2021 | APPLICANT |
| Plan Check Approved | 10/27/2021 | NILOOFAR MEHRAIN |
| Issued | 11/3/2021 | APPLICANT |
| CofO in Progress | 10/8/2022 | JEFFREY PARD |
| CofO Issued | 10/11/2022 | MICHAEL SMITH |
| Permit Finaled | 10/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 9/14/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 9/14/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 9/14/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 9/14/2021 | DANG NGUYEN |
| ZA Case | Cleared | 9/14/2021 | DANG NGUYEN |
| ZA Case | Cleared | 9/14/2021 | DANG NGUYEN |
| ZI | Cleared | 9/14/2021 | DANG NGUYEN |
| Address approval | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Permit | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 9/28/2021 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 10/19/2021 | ROBERT DUFF |
| GPI Written Notices | Cleared | 10/27/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 10/27/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/20/2021 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Rough | 1/11/2022 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 1/14/2022 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 1/27/2022 | Approved | HENRY KIM |
| Sewer | 2/24/2022 | Approved | HENRY KIM |
| Underground Mechanical | 3/8/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Partial Approval | HENRY KIM |
| Deputy Wood Construction | 4/13/2022 | Conditional Approval | HENRY KIM |
| ELECTRICAL-Rough | 5/12/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | HENRY KIM |
| HVAC-Rough | 5/12/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | HENRY KIM |
| Green Building Rough | 5/19/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/19/2022 | Approved | HENRY KIM |
| Shower Pan | 5/19/2022 | Approved | HENRY KIM |
| Special/Order Compliance | 5/19/2022 | Corrections Issued | HENRY KIM |
| Verify Sprinkler Sign Off | 5/19/2022 | Approved | HENRY KIM |
| HVAC-Final | 5/23/2022 | Corrections Issued | HENRY KIM |
| HVAC-Final | 5/25/2022 | Partial Inspection | HENRY KIM |
| Insulation | 5/31/2022 | Partial Approval | HENRY KIM |
| Drywall Nailing | 6/1/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/7/2022 | Approved | HENRY KIM |
| Gas Test | 7/8/2022 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Approved | HENRY KIM |
| Service/Power Release | 8/19/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/14/2022 | Approved | JEFFREY PARD |
| Gas Test | 9/14/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 9/14/2022 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Final | 9/14/2022 | Approved | JEFFREY PARD |
| Final | 9/22/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 9/22/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 9/22/2022 | Approved | JEFFREY PARD |
| Final | 10/3/2022 | Not Ready for Inspection | JEFFREY PARD |
| Final | 10/11/2022 | OK to Issue CofO | JEFFREY PARD |