12509 N SADDLE CT 91326

Certificate Information: 12509 N SADDLE CT 91326

Application / Permit
21010-20000-01743
Plan Check / Job No.
B21VN04252
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #654 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 10/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 NILOOFAR MEHRAIN
Corrections Issued 5/18/2021 NILOOFAR MEHRAIN
Quality Review Completed 5/18/2021 CHON CHIO KUO
Building Plans Picked Up 5/21/2021 APPLICANT
Plan Check Approved 10/27/2021 NILOOFAR MEHRAIN
Issued 11/3/2021 APPLICANT
CofO in Progress 10/12/2022 HENRY KIM
CofO Issued 10/12/2022 MICHAEL SMITH
Permit Finaled 10/12/2022 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 9/14/2021 DANG NGUYEN
Specific Plan Cleared 9/14/2021 DANG NGUYEN
Tract Map conditions Cleared 9/14/2021 DANG NGUYEN
Tract Map conditions Cleared 9/14/2021 DANG NGUYEN
ZA Case Cleared 9/14/2021 DANG NGUYEN
ZA Case Cleared 9/14/2021 DANG NGUYEN
ZI Cleared 9/14/2021 DANG NGUYEN
Address approval Cleared 9/15/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/15/2021 LEE GUILBEAUX
Permit Cleared 9/15/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/15/2021 LEE GUILBEAUX
Sewer availability Cleared 9/15/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/15/2021 LEE GUILBEAUX
Low Impact Development Cleared 9/28/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 10/19/2021 ROBERT DUFF
GPI Written Notices Cleared 10/27/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/27/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/20/2021 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 12/22/2021 Partial Approval HENRY KIM
PLUMBING-Rough 1/7/2022 Partial Approval HENRY KIM
Footing/Foundation/Slab 1/27/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval HENRY KIM
Sewer 2/24/2022 Approved HENRY KIM
Underground Mechanical 3/8/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Approval HENRY KIM
Deputy Reinf. Concrete 4/28/2022 Approved SEAN WIRCH
ELECTRICAL-Rough 5/10/2022 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Partial Approval HENRY KIM
HVAC-Rough 5/10/2022 Approved HENRY KIM
Deputy Drilled-In Anchors 5/12/2022 Approved SEAN WIRCH
ELECTRICAL-Rough 5/13/2022 Approved HENRY KIM
Interior/Exterior Lathing 5/13/2022 Partial Approval HENRY KIM
BUILDING-Rough-Frame 5/17/2022 Corrections Issued HENRY KIM
Green Building Rough 5/17/2022 Approved HENRY KIM
PLUMBING-Rough 5/17/2022 Approved HENRY KIM
Shower Pan 5/17/2022 Approved HENRY KIM
Verify Sprinkler Sign Off 5/17/2022 Approved HENRY KIM
BUILDING-Rough-Frame 5/20/2022 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 5/25/2022 Approved HENRY KIM
Drywall Nailing 5/31/2022 Approved HENRY KIM
Interior/Exterior Lathing 6/3/2022 Approved HENRY KIM
Gas Test 7/8/2022 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved HENRY KIM
Service/Power Release 8/23/2022 Approved HENRY KIM
ELECTRICAL-Final 9/13/2022 Approved JEFFREY PARD
Gas Test 9/13/2022 Approved JEFFREY PARD
HVAC-Final 9/13/2022 Approved JEFFREY PARD
PLUMBING-Final 9/13/2022 Approved JEFFREY PARD
Final 9/22/2022 Corrections Issued JEFFREY PARD
Green Building Final 9/22/2022 Approved JEFFREY PARD
Smoke Detectors 9/22/2022 Approved JEFFREY PARD
Final 10/3/2022 Not Ready for Inspection JEFFREY PARD
Final 10/12/2022 OK to Issue CofO HENRY KIM