12501 N SADDLE CT 91326

Certificate Information: 12501 N SADDLE CT 91326

Application / Permit
21010-20000-01740
Plan Check / Job No.
B21VN04252
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #654 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 NILOOFAR MEHRAIN
Corrections Issued 5/18/2021 NILOOFAR MEHRAIN
Quality Review Completed 5/18/2021 CHON CHIO KUO
Building Plans Picked Up 5/21/2021 APPLICANT
Plan Check Approved 10/27/2021 NILOOFAR MEHRAIN
Issued 11/3/2021 APPLICANT
CofO in Progress 9/30/2022 JEFFREY PARD
Permit Finaled 10/6/2022 MICHAEL SMITH
CofO Issued 10/6/2022 MICHAEL SMITH
Permit Finaled 10/6/2022 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 9/14/2021 DANG NGUYEN
Specific Plan Cleared 9/14/2021 DANG NGUYEN
Tract Map conditions Cleared 9/14/2021 DANG NGUYEN
Tract Map conditions Cleared 9/14/2021 DANG NGUYEN
ZA Case Cleared 9/14/2021 DANG NGUYEN
ZA Case Cleared 9/14/2021 DANG NGUYEN
ZI Cleared 9/14/2021 DANG NGUYEN
Address approval Cleared 9/15/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/15/2021 LEE GUILBEAUX
Permit Cleared 9/15/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/15/2021 LEE GUILBEAUX
Sewer availability Cleared 9/15/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/15/2021 LEE GUILBEAUX
Low Impact Development Cleared 9/28/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 10/19/2021 ROBERT DUFF
GPI Written Notices Cleared 10/27/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/27/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/8/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 1/14/2022 Approved HENRY KIM
Deputy Reinf. Concrete 1/18/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval HENRY KIM
Sewer 2/24/2022 Approved HENRY KIM
Underground Mechanical 3/8/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Corrections Issued HENRY KIM
Deputy Reinf. Concrete 4/28/2022 Approved SEAN WIRCH
Deputy Wood Construction 4/28/2022 Approved SEAN WIRCH
ELECTRICAL-Rough 4/29/2022 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval HENRY KIM
HVAC-Rough 4/29/2022 Approved HENRY KIM
Interior/Exterior Lathing 5/4/2022 Partial Approval HENRY KIM
BUILDING-Rough-Frame 5/6/2022 Corrections Issued HENRY KIM
ELECTRICAL-Rough 5/6/2022 Approved HENRY KIM
Green Building Rough 5/6/2022 Approved HENRY KIM
PLUMBING-Rough 5/6/2022 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 5/6/2022 Approved HENRY KIM
PLUMBING-Rough 5/10/2022 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 5/12/2022 Approved HENRY KIM
PLUMBING-Rough 5/12/2022 Approved HENRY KIM
Drywall Nailing 5/24/2022 Not Ready for Inspection HENRY KIM
Drywall Nailing 5/26/2022 Approved HENRY KIM
Interior/Exterior Lathing 5/26/2022 Partial Approval HENRY KIM
Interior/Exterior Lathing 6/6/2022 Approved HENRY KIM
Gas Test 7/8/2022 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved HENRY KIM
Service/Power Release 8/5/2022 Approved HENRY KIM
ELECTRICAL-Final 8/31/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Final 8/31/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 8/31/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 9/6/2022 Approved JEFFREY PARD
Green Building Final 9/6/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Final 9/6/2022 Approved JEFFREY PARD
PLUMBING-Final 9/6/2022 Approved JEFFREY PARD
Smoke Detectors 9/6/2022 Approved JEFFREY PARD
Final 9/9/2022 Not Ready for Inspection JEFFREY PARD
Green Building Final 9/9/2022 Corrections Issued JEFFREY PARD
Final 9/29/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 9/29/2022 Approved JEFFREY PARD