6708 N HINDS AVE 91606
Certificate Information: 6708 N HINDS AVE 91606
- Application / Permit
- 21010-20000-01721
- Plan Check / Job No.
- B21VN04184
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY, 42'-0" X 30'-3", 1200 SQ. FT. DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/18/2022
- Issuing Office
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | COLIN LOREDO |
| Corrections Issued | 5/20/2021 | COLIN LOREDO |
| Quality Review Completed | 6/3/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Plan Check Approved | 2/10/2022 | COLIN LOREDO |
| Issued | 2/18/2022 | APPLICANT |
| CofO in Progress | 10/24/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 12/22/2023 | RUBEN SALAS |
| CofO Issued | 12/22/2023 | RUBEN SALAS |
| Permit Finaled | 12/22/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/8/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/23/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/13/2023 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/17/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 3/17/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/22/2023 | Partial Approval | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 3/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 3/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 3/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/14/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 4/14/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 4/14/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 4/14/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 4/14/2023 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/14/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 4/19/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 4/19/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/24/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/24/2023 | Approved | JOHN HAYES |
| Green Building Rough | 4/24/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | JOHN HAYES |
| Green Building Rough | 4/27/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 4/27/2023 | Approved | JOHN HAYES |
| Insulation | 5/3/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/3/2023 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 5/5/2023 | Approved | JOHN HAYES |
| Shower Pan | 5/5/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/17/2023 | Approved | WILLIAM WREN |
| Sewer | 6/20/2023 | Approved | THOMAS FINNILA |
| Underground Mechanical | 7/6/2023 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Final | 8/3/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/3/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/3/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Final | 8/3/2023 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 8/3/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 10/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 10/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 10/4/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 10/4/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/4/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/4/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/4/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/11/2023 | Corrections Issued | JOHN HAYES |
| Gas Test | 10/11/2023 | Approved | JOHN HAYES |
| HVAC-Final | 10/11/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 10/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 10/11/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/24/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/24/2023 | Not Required | JENNIFER RABUCHIN |