4137 N MARY ELLEN AVE 91604

Certificate Information: 4137 N MARY ELLEN AVE 91604

Application / Permit
21010-20000-01720
Plan Check / Job No.
B21VN04183
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 1/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 SELLA BENYAMIN
Corrections Issued 4/20/2021 SELLA BENYAMIN
Quality Review Completed 4/21/2021 STEVEN KIM
Plan Check Approved 8/10/2021 SELLA BENYAMIN
Issued 8/12/2021 APPLICANT
CofO in Progress 1/9/2023 CHRISTOPHE COCHRAN
CofO in Progress 1/9/2023 CHRISTOPHE COCHRAN
CofO Issued 1/10/2023 MICHAEL SMITH
Permit Finaled 1/10/2023 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 4/28/2021 GUILLERMO PETRA
Watercourse Cleared 4/28/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/29/2021 GUILLERMO PETRA
Sewer availability Cleared 4/29/2021 GUILLERMO PETRA
Trees in Parkway Cleared 5/20/2021 JOHN KIM
Hydrant and Access approval Cleared 6/9/2021 MATTHEW CRAIG
ZI Cleared 7/1/2021 LAUREN PADICK
Low Impact Development Cleared 7/21/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/28/2021 DAGOVERTO GUERRERO
GPI Written Notices Cleared 8/10/2021 SELLA BENYAMIN
Grading Pre-Inspection Cleared 8/10/2021 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/20/2021 Approved ARAM AVEDISIAN
Underground Mechanical 10/20/2021 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/23/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/23/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/1/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Approved MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Conditional Approval ARAM AVEDISIAN
Pre-Inspection 2/3/2022 Partial Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Conditional Approval ARAM AVEDISIAN
Underground Mechanical 4/18/2022 Partial Approval CALEB MEISTER
PLUMBING-Rough 4/25/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 4/28/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 4/28/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 5/3/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 5/10/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/10/2022 Approved ARAM AVEDISIAN
HVAC-Rough 5/10/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/19/2022 Approved CALEB MEISTER
Shower Pan 5/19/2022 Approved CALEB MEISTER
Insulation 5/27/2022 Corrections Issued CALEB MEISTER
Drywall Nailing 6/16/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/27/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/14/2022 Approved CHRISTOPHE COCHRAN
Final 12/14/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 12/14/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 12/14/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Not Ready CHRISTOPHE COCHRAN
Service/Power Release 12/14/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 12/14/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 12/14/2022 Approved CHRISTOPHE COCHRAN
Final 12/28/2022 OK to Issue CofO CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 12/28/2022 Approved CHRISTOPHE COCHRAN