17321 W RANCHO ST 91316
Certificate Information: 17321 W RANCHO ST 91316
- Application / Permit
- 21010-20000-01710
- Plan Check / Job No.
- B21VN04159
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (126'-0"x 114'-6") TWO-STORY SINGLE FAMILY DWELLING W/ATT 2-CAR GARAGE OVER BASEMENT. NFPA-13D AUTO FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 10/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | TROY DEGUZMAN |
| Corrections Issued | 4/17/2021 | TROY DEGUZMAN |
| Quality Review Completed | 4/19/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 11/29/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 2/15/2022 | TROY DEGUZMAN |
| Plan Check Approved | 2/18/2022 | TROY DEGUZMAN |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 8/14/2024 | MORRIS JACKSON |
| CofO in Progress | 9/3/2024 | SEAN WIRCH |
| Permit Finaled | 10/18/2024 | JOHN JANSON |
| CofO Issued | 10/18/2024 | JOHN JANSON |
| Permit Finaled | 10/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/17/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 4/17/2021 | TROY DEGUZMAN |
| Address approval | Cleared | 5/6/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/6/2021 | GABRIEL ROBLES |
| Watercourse | Cleared | 5/7/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 8/16/2021 | MATTHEW CRAIG |
| Permit | Cleared | 12/1/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 12/13/2021 | TROY DEGUZMAN |
| Low Impact Development | Cleared | 2/2/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/4/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | E T Development Inc; Lic. No.: 994749-B | 7256 BELLAIRE AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/10/2022 | Partial Approval | ROBERT GOLD |
| Deputy Reinf. Concrete | 7/8/2022 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/12/2022 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/13/2022 | Partial Approval | SEAN HAUPT |
| Deputy Shotcrete | 7/13/2022 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/25/2022 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/25/2022 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 8/5/2022 | Conditional Approval | JOHN JANSON |
| Underground Mechanical | 9/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 10/3/2022 | Approved | SEAN HAUPT |
| Deputy Other (see comments) | 10/7/2022 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 10/12/2022 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 10/12/2022 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 10/21/2022 | Conditional Approval | MORRIS JACKSON |
| Deputy Steel/Welding | 10/26/2022 | Conditional Approval | MORRIS JACKSON |
| Deputy Wood Construction | 10/27/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 3/8/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Approved | JON MCHUGH |
| Special/Order Compliance | 3/20/2023 | Partial Inspection | SEAN WIRCH |
| HVAC-Rough | 4/4/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 4/13/2023 | Corrections Issued | JON MCHUGH |
| Shower Pan | 4/13/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 4/26/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 4/26/2023 | Approved | JON MCHUGH |
| Green Building Rough | 4/26/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 4/26/2023 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 4/26/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 5/19/2023 | Partial Approval | SEAN WIRCH |
| Green Building Rough | 5/19/2023 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 5/19/2023 | Partial Approval | SEAN WIRCH |
| Verify Sprinkler Sign Off | 5/19/2023 | Approved | SEAN WIRCH |
| Insulation | 5/23/2023 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 5/31/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 6/6/2023 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 4/1/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 4/1/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 5/7/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 5/7/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 5/7/2024 | Corrections Issued | JON MCHUGH |
| Gas Test | 5/30/2024 | Approved | JON MCHUGH |
| HVAC-Final | 5/30/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 5/30/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 6/5/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 6/10/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 7/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Final | 7/24/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 7/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Reinforced Concrete Frame | 7/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 7/29/2024 | Approved | JON MCHUGH |
| Final | 7/29/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 7/29/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 7/29/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 7/29/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/31/2024 | Corrections Issued | JON MCHUGH |
| Gas Test | 7/31/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/31/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | JON MCHUGH |
| Final | 8/2/2024 | Corrections Issued | JON MCHUGH |
| Reinforced Concrete Frame | 8/2/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | JON MCHUGH |
| ELECTRICAL-Final | 8/12/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 8/12/2024 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Final | 8/13/2024 | Approved | MORRIS JACKSON |
| Final | 8/13/2024 | OK to Issue CofO | MORRIS JACKSON |