4793 N LOUISE AVE 91316

Certificate Information: 4793 N LOUISE AVE 91316

Application / Permit
21010-20000-01708
Plan Check / Job No.
B21VN04154
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW (18'-2"x 13'-0") DETACHED COVERED PATIO. WORK PER ENGINEER.
Permit Issued
Issued on 12/21/2021
Issuing Office
Valley
Current Status
CofO Corrected on 10/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 TROY DEGUZMAN
Corrections Issued 4/18/2021 TROY DEGUZMAN
Quality Review Completed 4/19/2021 OMID HEDAYAT
Applicant returned to address corrections 11/10/2021 TROY DEGUZMAN
Applicant returned to address corrections 11/29/2021 TROY DEGUZMAN
Plan Check Approved 12/15/2021 TROY DEGUZMAN
Issued 12/21/2021 APPLICANT
CofO in Progress 10/6/2023 JON MCHUGH
CofO Issued-Status Void 10/13/2023 JOHN JANSON
Permit Finaled-Status Void 10/13/2023 JOHN JANSON
Re-Activate Permit 10/16/2023 JOHN JANSON
CofO Corrected 10/16/2023 JOHN JANSON
Permit Finaled 10/16/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/17/2021 TROY DEGUZMAN
Green Code Cleared 4/17/2021 TROY DEGUZMAN
Sewer availability Cleared 7/8/2021 GABRIEL ROBLES
Watercourse Cleared 7/8/2021 GABRIEL ROBLES
Low Impact Development Cleared 12/3/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/6/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 12/7/2021 ABDULLAH SADOZAI

Contact Information

Contractor E T Development Inc; Lic. No.: 994749-B 7256 BELLAIRE AVENUE      NORTH HOLLYWOOD, CA 91605
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/15/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 2/16/2023 Not Ready for Inspection SEAN HAUPT
Footing/Foundation/Slab 2/22/2023 Approved JON MCHUGH
Deputy Wood Construction 3/8/2023 Conditional Approval JON MCHUGH
ELECTRICAL-Rough 3/20/2023 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 3/29/2023 Approved JON MCHUGH
Interior/Exterior Lathing 3/29/2023 Partial Approval JON MCHUGH
Rough-Elec/Plmb/HVAC 3/29/2023 Approved JON MCHUGH
Verify Sprinkler Sign Off 3/29/2023 Approved JON MCHUGH
Interior/Exterior Lathing 4/13/2023 Approved JON MCHUGH
Shower Pan 4/13/2023 Approved JON MCHUGH
Drywall Nailing 5/1/2023 Approved JON MCHUGH
ELECTRICAL-Final 9/26/2023 Approved JON MCHUGH
Final 9/26/2023 Partial Approval JON MCHUGH
HVAC-Final 9/26/2023 Approved JON MCHUGH
PLUMBING-Final 9/26/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved JON MCHUGH
Service/Power Release 9/26/2023 Approved JON MCHUGH
Smoke Detectors 9/26/2023 Approved JON MCHUGH
Final 10/10/2023 OK to Issue CofO JON MCHUGH