8128 N VANTAGE AVE 91605
Certificate Information: 8128 N VANTAGE AVE 91605
- Application / Permit
- 21010-20000-01668
- Plan Check / Job No.
- B21VN04040
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT (25'-0"X25'-0"). ALL WORK PER WOOD FRAMED PRESCRIPTIVE PROVISIONS per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Current Status
- CofO Issued on 4/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | ALYSSA N NARCISO |
| Corrections Issued | 6/2/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 6/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Plan Check Approved | 1/3/2022 | MOHAMMAD ESMAILI |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 4/27/2023 | MATTHEW NELSON |
| Permit Finaled | 4/27/2023 | MICHAEL SMITH |
| CofO Issued | 4/27/2023 | MICHAEL SMITH |
| Permit Finaled | 4/27/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/21/2021 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 6/24/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/24/2021 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 9/28/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/17/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 1/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 2/9/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/9/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/14/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/14/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 2/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 2/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/18/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 7/19/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 7/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 4/20/2023 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 4/20/2023 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 4/26/2023 | Approved | MATTHEW NELSON |
| Final | 4/26/2023 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 4/26/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 4/26/2023 | Approved | MATTHEW NELSON |
| Service/Power Release | 4/26/2023 | Approved | MATTHEW NELSON |