NEW 2-STORY IRREGULAR SHAPED 68'-7"X 41'-8", 3,425 SQ. FT. SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
CofO Issued on 12/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 COLIN LOREDO
Corrections Issued 4/12/2021 COLIN LOREDO
Quality Review Completed 4/15/2021 OMID HEDAYAT
Applicant returned to address corrections 9/14/2021 COLIN LOREDO
Applicant returned to address corrections 10/5/2021 COLIN LOREDO
Plan Check Approved 10/5/2021 COLIN LOREDO
Issued 10/7/2021 APPLICANT
CofO in Progress 12/1/2022 THOMAS FINNILA
CofO Issued 12/6/2022 MICHAEL SMITH
Permit Finaled 12/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/21/2021 ADRIAN CASTRO
Sewer availability Cleared 5/21/2021 ADRIAN CASTRO
Low Impact Development Cleared 8/23/2021 YVAINNE GALSIM
Hydrant and Access approval Cleared 9/13/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 10/6/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/29/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/7/2022 Approved JACK KARGODORIAN
Footing/Foundation/Slab 4/7/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 5/11/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 5/11/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 5/11/2022 Approved JACK KARGODORIAN
Deputy Wood Construction 5/12/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 5/13/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Approved JACK KARGODORIAN
Deputy Steel/Welding 5/25/2022 Partial Approval JACK KARGODORIAN
Shower Pan 5/25/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 6/16/2022 Approved JACK KARGODORIAN
Green Building Rough 6/16/2022 Approved JACK KARGODORIAN
MERV13>=Rough 6/16/2022 Approved JACK KARGODORIAN
Shower Pan 6/16/2022 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 6/16/2022 Approved JACK KARGODORIAN
Wood Frame 6/16/2022 Approved JACK KARGODORIAN
Insulation 6/23/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/23/2022 Approved JACK KARGODORIAN
Drywall Nailing 7/1/2022 Corrections Issued JACK KARGODORIAN
Drywall Nailing 7/8/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 10/28/2022 Corrections Issued THOMAS FINNILA
HVAC-Final 10/28/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 10/28/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 11/3/2022 Approved JACK KARGODORIAN
HVAC-Final 11/3/2022 Approved JACK KARGODORIAN
PLUMBING-Final 11/3/2022 Approved JACK KARGODORIAN
Final 11/9/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 11/9/2022 Approved MISAEL ESPARZA
MERV13>=Final 11/9/2022 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 11/9/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/9/2022 Approved MISAEL ESPARZA
Final 11/28/2022 Partial Inspection THOMAS FINNILA
MERV13>=Final 11/28/2022 Approved THOMAS FINNILA
Service/Power Release 11/28/2022 Not Ready for Inspection THOMAS FINNILA
Final 12/1/2022 OK to Issue CofO THOMAS FINNILA
Service/Power Release 12/1/2022 Approved THOMAS FINNILA