11725 W HESBY ST 91607
Certificate Information: 11725 W HESBY ST 91607
- Application / Permit
- 21010-20000-01635
- Plan Check / Job No.
- B21VN03981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW REC. ROOM w/ POOL BATH (19'-6"x13'-0")
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | CHON CHIO KUO |
| Corrections Issued | 4/12/2021 | CHON CHIO KUO |
| Quality Review Completed | 4/15/2021 | STEVEN KIM |
| Applicant returned to address corrections | 10/14/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/10/2021 | MOHAMMAD ESMAILI |
| Issued | 11/10/2021 | APPLICANT |
| CofO in Progress | 10/31/2022 | JACK KARGODORIAN |
| Permit Finaled | 11/3/2022 | MICHAEL SMITH |
| CofO Issued | 11/3/2022 | MICHAEL SMITH |
| Permit Finaled | 11/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/28/2021 | ANDREW JORGENSEN |
| ZI | Cleared | 6/28/2021 | ANDREW JORGENSEN |
| ZI | Cleared | 6/28/2021 | ANDREW JORGENSEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/29/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 8/30/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 9/10/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/27/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2021 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 12/1/2021 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 12/8/2021 | Corrections Issued | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Approved | MATT KELLERMAN |
| Footing/Foundation/Slab | 12/17/2021 | Approved | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 1/25/2022 | Conditional Approval | CALEB MEISTER |
| PLUMBING-Rough | 1/25/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/7/2022 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 2/7/2022 | Approved | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 2/7/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 2/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/22/2022 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 2/22/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/28/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/3/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/10/2022 | Approved | DAVID MATSON |
| Insulation | 3/21/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 8/31/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 8/31/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 9/19/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 9/22/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 10/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 10/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 10/6/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 10/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/19/2022 | Approved | JACK KARGODORIAN |
| Final | 10/19/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 10/19/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 10/19/2022 | Approved | JACK KARGODORIAN |
| Service/Power Release | 10/19/2022 | Approved | JACK KARGODORIAN |
| Verify Rec and Parks Fee Memo | 10/19/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/28/2022 | Approved | JACK KARGODORIAN |
| Final | 10/28/2022 | OK to Issue CofO | JACK KARGODORIAN |
| HVAC-Final | 10/28/2022 | Approved | JACK KARGODORIAN |