11725 W HESBY ST 91607

Certificate Information: 11725 W HESBY ST 91607

Application / Permit
21010-20000-01634
Plan Check / Job No.
B21VN03981
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD/GAR (58'-1"X53'-0") FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 11/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 CHON CHIO KUO
Corrections Issued 4/12/2021 CHON CHIO KUO
Quality Review Completed 4/15/2021 STEVEN KIM
Applicant returned to address corrections 10/14/2021 MOHAMMAD ESMAILI
Plan Check Approved 11/10/2021 MOHAMMAD ESMAILI
Issued 11/10/2021 APPLICANT
CofO in Progress 10/31/2022 JACK KARGODORIAN
CofO Issued 11/3/2022 MICHAEL SMITH
Permit Finaled 11/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/21/2021 GABRIEL ROBLES
Permit Cleared 5/21/2021 GABRIEL ROBLES
Work Adjacent to Public Way Cleared 5/21/2021 GABRIEL ROBLES
Sewer availability Cleared 6/28/2021 GABRIEL ROBLES
Specific Plan Cleared 6/28/2021 ANDREW JORGENSEN
ZI Cleared 6/28/2021 ANDREW JORGENSEN
ZI Cleared 6/28/2021 ANDREW JORGENSEN
Hydrant and Access approval Cleared 8/30/2021 KURT CORRAL
Low Impact Development Cleared 9/10/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 9/22/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/29/2021 Conditional Approval THOMAS FINNILA
Underground Mechanical 12/1/2021 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 12/8/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 12/8/2021 Corrections Issued MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 12/17/2021 Approved MATT KELLERMAN
Footing/Foundation/Slab 12/17/2021 Approved MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 1/25/2022 Approved CALEB MEISTER
PLUMBING-Rough 1/25/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 2/7/2022 Partial Approval MATT KELLERMAN
Green Building Rough 2/7/2022 Approved MATT KELLERMAN
Verify Sprinkler Sign Off 2/7/2022 Approved MATT KELLERMAN
BUILDING-Rough-Frame 2/22/2022 Approved MATT KELLERMAN
ELECTRICAL-Rough 2/22/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 2/22/2022 Approved MATT KELLERMAN
Shower Pan 2/22/2022 Approved THOMAS FINNILA
ELECTRICAL-Rough 2/28/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/3/2022 Approved CALEB MEISTER
ELECTRICAL-Rough 3/10/2022 Approved DAVID MATSON
Insulation 3/21/2022 Approved THOMAS FINNILA
Drywall Nailing 3/29/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 8/31/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 8/31/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 9/19/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 9/22/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 9/22/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/6/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 10/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 10/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 10/6/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/19/2022 Approved JACK KARGODORIAN
Final 10/19/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 10/19/2022 Approved JACK KARGODORIAN
PLUMBING-Final 10/19/2022 Approved JACK KARGODORIAN
Service/Power Release 10/19/2022 Approved JACK KARGODORIAN
Verify Rec and Parks Fee Memo 10/19/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 10/27/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 10/27/2022 Approved JACK KARGODORIAN
PLUMBING-Final 10/27/2022 Approved JACK KARGODORIAN
Service/Power Release 10/27/2022 Approved JACK KARGODORIAN
Final 10/28/2022 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 10/28/2022 Approved JACK KARGODORIAN