18216 W ACRE ST 91325

Certificate Information: 18216 W ACRE ST 91325

Application / Permit
21010-20000-01633
Plan Check / Job No.
B21VN03949
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 44' X 43'9" DETACHED ACCESSORY DWELLING UNIT TYPE V-A WITH ATTACHED TWO CAR GARAGE AS PER LAMC.12.22.33 (C) AND (E), NFPA-13D FIRE SPRINKLERS , ALL WORK PER WFPP- SEE COMMENTS
Permit Issued
Issued on 8/4/2023
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 RARES BODEA
Corrections Issued 5/9/2021 RARES BODEA
Quality Review Completed 5/18/2021 STEVEN KIM
Building Plans Picked Up 5/18/2021 APPLICANT
Applicant returned to address corrections 9/28/2022 RARES BODEA
Applicant returned to address corrections 11/10/2022 RARES BODEA
Applicant returned to address corrections 2/7/2023 RARES BODEA
Applicant returned to address corrections 2/23/2023 RARES BODEA
Applicant returned to address corrections 6/22/2023 RARES BODEA
Plan Check Approved 8/4/2023 RARES BODEA
Issued 8/4/2023 APPLICANT
CofO in Progress 11/12/2024 DAVID SCANTLIN
Permit Finaled 11/13/2024 JOHN JANSON
CofO Issued 11/13/2024 JOHN JANSON
Permit Finaled 11/13/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/19/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/14/2021 GABRIEL ROBLES
Sewer availability Cleared 7/14/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/1/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/18/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/29/2021 ROBERT DUFF
Permit Cleared 2/17/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 3/31/2023 WALTER RAMIREZ
Highway dedication Cleared 6/21/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/21/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 9/27/2023 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 1/25/2024 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 1/31/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 1/31/2024 Approved DAVID SCANTLIN
Green Building Rough 1/31/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/31/2024 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 1/31/2024 Approved DAVID SCANTLIN
Drywall Nailing 2/12/2024 Approved KRISTEN CAUSEY
Shower Pan 2/12/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 2/22/2024 Approved DAVID SCANTLIN
Underground Mechanical 3/28/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Final 8/15/2024 Partial Inspection KRISTEN CAUSEY
Service/Power Release 8/15/2024 Partial Inspection KRISTEN CAUSEY
Final 8/30/2024 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Final 9/26/2024 Approved DAVID SCANTLIN
HVAC-Final 9/26/2024 Approved DAVID SCANTLIN
PLUMBING-Final 9/26/2024 Approved DAVID SCANTLIN
Service/Power Release 9/26/2024 Approved DAVID SCANTLIN
Final 10/2/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 10/2/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 10/2/2024 Approved DAVID SCANTLIN
PLUMBING-Final 10/2/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV No Gas DAVID SCANTLIN
Service/Power Release 10/2/2024 Approved DAVID SCANTLIN
Smoke Detectors 10/2/2024 Approved DAVID SCANTLIN
Final 11/13/2024 OK to Issue CofO DAVID SCANTLIN
Green Building Final 11/13/2024 Approved DAVID SCANTLIN