4990 N VANALDEN AVE 91356
Certificate Information: 4990 N VANALDEN AVE 91356
- Application / Permit
- 21010-20000-01626
- Plan Check / Job No.
- B21VN03941
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 8/30/2021
- Issuing Office
- Valley
- Current Status
- Pending
- Certificate of Occupancy
- CofO Issued More Information
Pre - Inspection only, not a permit for construction
Permit Application Status History
| Submitted | 4/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/11/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/19/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/30/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/10/2021 | NILOOFAR MEHRAIN |
| Issued | 8/30/2021 | APPLICANT |
| CofO in Progress | 5/17/2023 | SEAN HAUPT |
| Permit Finaled | 6/1/2023 | JOHN JANSON |
| CofO Issued | 6/1/2023 | JOHN JANSON |
| Permit Finaled | 6/1/2023 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/13/2021 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/21/2021 | GUILLERMO PETRA |
| Street Frontage | Cleared | 4/30/2021 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 5/18/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/23/2021 | ROBERT DUFF |
| GPI Written Notices | Cleared | 7/30/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 7/30/2021 | NILOOFAR MEHRAIN |
| Low Impact Development | Cleared | 7/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/31/2021 | GABRIEL ROBLES |
| Permit | Cleared | 8/2/2021 | LEE GUILBEAUX |
| Grading Preinspection | Cleared | 8/10/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dejban,, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/12/2021 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/12/2021 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 11/12/2021 | Partial Inspection | DAVID SANDOVAL |
| Underground Mechanical | 11/23/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 12/9/2021 | No Access for Inspection | ROBERT GOLD |
| Footing/Foundation/Slab | 12/9/2021 | No Access for Inspection | ROBERT GOLD |
| Footing/Foundation/Slab | 12/10/2021 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 1/19/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Wood Construction | 3/2/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 3/17/2022 | Partial Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 5/2/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 5/2/2022 | Approved | DAVID SANDOVAL |
| Gas Test | 5/16/2022 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 5/16/2022 | Corrections Issued | DAVID SANDOVAL |
| Insulation | 5/16/2022 | Partial Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/25/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 5/25/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 5/25/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 5/25/2022 | Approved | DAVID SANDOVAL |
| Insulation | 7/13/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 7/29/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 7/29/2022 | Partial Approval | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/16/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 8/16/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 2/22/2023 | Approved | DAVID SANDOVAL |
| HVAC-Final | 2/22/2023 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 2/22/2023 | Approved | DAVID SANDOVAL |
| Gas Test | 3/22/2023 | Approved | DAVID SANDOVAL |
| Final | 5/16/2023 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 5/16/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 5/16/2023 | Approved | SEAN HAUPT |
| Smoke Detectors | 5/16/2023 | Approved | SEAN HAUPT |