4436 N KATHERINE AVE 91423

Certificate Information: 4436 N KATHERINE AVE 91423

Application / Permit
21010-20000-01617
Plan Check / Job No.
B21VN01968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 13'-0" X 19'-6" IRREGULAR SHAPED RECROOM WITH BATHROOM (EXTERIOR ACCESS ONLY).
Permit Issued
Issued on 11/30/2021
Issuing Office
Current Status
CofO Issued on 12/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 ARTIN ZARUKIAN
Corrections Issued 4/3/2021 ARTIN ZARUKIAN
Quality Review Completed 4/9/2021 STEVEN KIM
Applicant returned to address corrections 10/14/2021 ARTIN ZARUKIAN
Plan Check Approved 11/18/2021 ARTIN ZARUKIAN
Issued 11/30/2021 APPLICANT
Building Plans Picked Up 12/2/2021 APPLICANT
CofO in Progress 12/16/2022 MISAEL ESPARZA
CofO Issued 12/19/2022 MICHAEL SMITH
Permit Finaled 12/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/1/2021 CARLOS AGUILERA
Construction near power lines Cleared 9/3/2021 RIDWAN HARDY
ZI Cleared 9/7/2021 MIGUEL GAMBOA
Low Impact Development Cleared 9/20/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/21/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/13/2022 Approved MISAEL ESPARZA
Footing/Foundation/Slab 1/25/2022 Conditional Approval MISAEL ESPARZA
HVAC-Rough 3/4/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/4/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 3/7/2022 Approved MISAEL ESPARZA
Green Building Rough 3/7/2022 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 3/7/2022 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 3/7/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 3/16/2022 Conditional Approval MISAEL ESPARZA
Green Building Rough 3/16/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 3/16/2022 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 3/16/2022 Approved MISAEL ESPARZA
Wood Frame 3/16/2022 Approved MISAEL ESPARZA
Insulation 3/23/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/23/2022 Partial Approval MISAEL ESPARZA
Green Building Rough 4/4/2022 Approved MISAEL ESPARZA
Shower Pan 4/4/2022 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 4/7/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 4/7/2022 Approved ASHLEY THOMPSON
Shower Pan 4/7/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 11/4/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 11/4/2022 Approved MISAEL ESPARZA
Final 11/4/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/4/2022 Approved MISAEL ESPARZA
Green Building Final 11/4/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 11/4/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 11/4/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 11/4/2022 Not Required MISAEL ESPARZA
Smoke Detectors 11/4/2022 Approved MISAEL ESPARZA
Final 12/14/2022 OK to Issue CofO MISAEL ESPARZA
Green Building Final 12/14/2022 Approved MISAEL ESPARZA