14822 W HESBY ST 91403
Certificate Information: 14822 W HESBY ST 91403
- Application / Permit
- 21010-20000-01532
- Plan Check / Job No.
- B21VN03789
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 70'-6" X 38'-0" TWO-STORY SINGLE FAMILY DWELLING W/GARAGE. ALL WORK PER ENGINEER. ** NFPA 13-D AUTOMATIC FIRE SPRINKLER THROUGHOUT BUILDING **
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | PARISA ZAHABI |
| Corrections Issued | 4/14/2021 | PARISA ZAHABI |
| Quality Review Completed | 4/21/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/26/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/15/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/19/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/22/2021 | PARISA ZAHABI |
| Plan Check Approved | 7/27/2021 | PARISA ZAHABI |
| Issued | 7/27/2021 | APPLICANT |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| CofO in Progress | 4/15/2022 | JACK KARGODORIAN |
| Permit Finaled | 4/19/2022 | MICHAEL SMITH |
| CofO Issued | 4/19/2022 | MICHAEL SMITH |
| Permit Finaled | 4/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Permit | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 6/8/2021 | ROBERT DUFF |
| CPC | Cleared | 6/18/2021 | DANG NGUYEN |
| ZI | Cleared | 6/18/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 7/8/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/8/2021 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 7/8/2021 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/5/2021 | Approved | CHARLES POWELL |
| Footing/Foundation/Slab | 8/12/2021 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Partial Approval | CHARLES POWELL |
| Deputy Wood Construction | 9/15/2021 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/15/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/15/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 9/20/2021 | Approved | MISAEL ESPARZA |
| Shower Pan | 9/28/2021 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 10/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 10/12/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 10/12/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/18/2021 | Partial Inspection | JACK KARGODORIAN |
| Green Building Rough | 10/18/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/18/2021 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/26/2021 | Partial Approval | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Not Ready | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/16/2022 | Conditional Approval | JACK KARGODORIAN |
| Drywall Nailing | 3/16/2022 | Approved | JACK KARGODORIAN |
| Final | 3/16/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 3/16/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/16/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 3/16/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 3/16/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/16/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/15/2022 | Approved | JACK KARGODORIAN |
| Final | 4/15/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 4/15/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 4/15/2022 | Approved | JACK KARGODORIAN |