16022 W NAPA ST 91343

Certificate Information: 16022 W NAPA ST 91343

Application / Permit
21010-20000-01531
Plan Check / Job No.
B21VN03786
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 43'-6" x 27'-9" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/15/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 SELLA BENYAMIN
Corrections Issued 5/4/2021 SELLA BENYAMIN
Quality Review Completed 5/11/2021 STEVEN KIM
Building Plans Picked Up 5/17/2021 APPLICANT
Plan Check Approved 6/2/2023 SELLA BENYAMIN
Issued 5/15/2024 APPLICANT
CofO in Progress 8/11/2025 OGANES TARAKHCHYAN
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/21/2022 CARLOS AGUILERA
Sewer availability Cleared 1/21/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/5/2022 DWIGHT SANKEY
Low Impact Development Cleared 3/25/2022 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 12/21/2022 CARLOS AGUILERA
Construction near power lines Cleared 12/29/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 1/11/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/17/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/22/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 5/29/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 5/29/2024 Approved RAUL OLAGI
Sewer 7/2/2024 Approved RAUL OLAGI
Underground Mechanical 7/2/2024 Partial Approval RAUL OLAGI
Deputy Wood Construction 7/22/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 9/9/2024 Corrections Issued RAUL OLAGI
Underground Mechanical 9/9/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 9/10/2024 Corrections Issued RAUL OLAGI
HVAC-Rough 9/10/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 9/11/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 9/11/2024 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 9/11/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 9/16/2024 Approved RAUL OLAGI
HVAC-Rough 9/16/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 9/16/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 10/25/2024 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 11/4/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 11/6/2024 Approved GAREN HAYRAPETYAN
Wood Frame 11/6/2024 Conditional Approval GAREN HAYRAPETYAN
Insulation 11/19/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 11/27/2024 Approved LOUIS ESCOTO
Shower Pan 1/22/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 7/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
Service/Power Release 7/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/23/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 7/23/2025 Corrections Issued SALVADOR MARTINEZ
Final 7/23/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 7/23/2025 Approved SALVADOR MARTINEZ
Green Building Rough 7/23/2025 Approved SALVADOR MARTINEZ
HVAC-Final 7/23/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 7/23/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 7/23/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Final 8/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Service/Power Release 8/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/8/2025 Approved OGANES TARAKHCHYAN
Final 8/8/2025 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 8/8/2025 Approved OGANES TARAKHCHYAN