10068 N ARLETA AVE 91331
Certificate Information: 10068 N ARLETA AVE 91331
- Application / Permit
- 21010-20000-01526
- Plan Check / Job No.
- B21VN03770
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY 480 SQ. FT. ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT PER LAFD. ALL WORK SHALL CONFORM TO THE WFPP.
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | COLIN LOREDO |
| Corrections Issued | 5/11/2021 | COLIN LOREDO |
| Quality Review Completed | 5/18/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 5/19/2021 | APPLICANT |
| Plan Check Approved | 12/21/2021 | COLIN LOREDO |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 11/21/2022 | MICHEL ABAJAN |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
| CofO Issued | 12/10/2022 | MICHAEL SMITH |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/13/2021 | RIDWAN HARDY |
| Address approval | Cleared | 7/27/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/27/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 11/8/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2022 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 2/10/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 2/10/2022 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 2/18/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 2/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/1/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/1/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 3/16/2022 | Partial Approval | MICHEL ABAJAN |
| Gas Test | 4/8/2022 | Partial Approval | MICHEL ABAJAN |
| Sewer | 4/8/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/12/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/12/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | MICHEL ABAJAN |
| Gas Test | 5/12/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/12/2022 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 5/12/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/12/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/12/2022 | Partial Inspection | MICHEL ABAJAN |
| Wood Frame | 6/7/2022 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Rough | 6/30/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 6/30/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 6/30/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/18/2022 | Approved | MICHEL ABAJAN |
| Final | 11/18/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 11/18/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/18/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 11/18/2022 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/18/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/18/2022 | Approved | MICHEL ABAJAN |